Amending network diagrams | AQA A-Level Business
Updated: 14 hours ago
For Specification 7132
AQA A-Level Business | Free Revision Notes
Estimated study time: 40 to 45 minutes
Project plans do not always develop exactly as expected. An activity may take longer or less time than originally estimated, changing the project's critical path, available float and completion date. These Amending network diagrams A-Level Business revision notes explain how to update network information when activity timings change and how managers can use the revised information during strategic implementation. This builds directly on network analysis [Lesson 145. Network analysis] and critical paths and total float [Lesson 146. Critical paths and total float].
Learning Objectives 🎯
By the end of this revision page, you should be able to:
Interpret changes in activity timings.
Amend network diagrams when an activity duration changes.
Recalculate the duration of project routes.
Reassess the critical path following a change.
Recalculate relevant total float.
Analyse how changes in network information may affect strategic implementation decisions.
Revision Notes 📚
Amending network diagrams A-Level Business revision overview
AQA's network-analysis content includes:
understanding and interpreting network diagrams
amendment of network diagrams
identifying the critical path
identifying total float
The original network is based on expected activity durations.
However, strategic implementation takes place in an uncertain business environment.
An activity might:
take longer than expected
be completed more quickly
experience an unexpected delay
When this happens, managers need to reconsider the network.
The process can involve:
activity timing changes → network is amended → route durations are recalculated → critical path is reassessed → float may change → implementation decisions may need to change
The important principle is:
A network diagram is not fixed. If the information changes, the project analysis must also be updated.
Why might a network need to be amended?
Network diagrams contain estimates of how long project activities are expected to take.
Actual durations may differ.
For example:
equipment installation takes longer than expected
an approval process is completed early
a supplier causes a delay
an activity encounters an unexpected problem
work is completed more quickly than planned
If management continues using the original network after activity timings change, its information about:
the project duration
the critical path
available float
may become inaccurate.
Example
Original Activity E:
4 days
New information:
Activity E will take 7 days
Increase:
7 - 4 = 3 days
Management cannot simply add three days to the total project duration.
Whether the project completion date changes depends on:
whether E was critical
how much float E had
which route E belongs to
whether the longer duration creates a new critical path
This is why the whole network may need to be reconsidered.
First question: was the changed activity critical?
When an activity duration changes, identify whether it was originally:
on the critical path
off the critical path
This gives an initial indication of the likely effect.
If a critical activity takes longer
Critical activities have zero total float.
Therefore:
critical activity duration increases → no existing float to absorb increase → critical route becomes longer → project completion may also become later
For example:
Original critical path:
A → C → F = 16 days
C originally takes 8 days.
If C now takes 10 days:
A → C → F = 6 + 10 + 2 = 18 days
If no other network changes occur, the project duration increases from:
16 days to 18 days
If a non-critical activity takes longer
The result is less immediate.
A non-critical activity may have float.
For example:
Activity D has:
6 days total float
D becomes:
3 days longer
Since:
3-day increase < 6-day float
the increase can potentially be absorbed.
The overall project duration need not change.
Remaining float may fall to:
6 - 3 = 3 days
However, if D becomes longer by more than its available float, the route containing D may begin to affect overall completion.
Changes to non-critical activities can create new critical paths
This is one of the most important ideas in the topic.
Suppose the original routes are:
Route ACF = 16 days
Route BDF = 10 days
Route BEG = 15 days
The original critical path is:
ACF
because it is the longest route.
Now suppose Activity E increases by three days.
The route BEG becomes:
18 days
The routes are now:
ACF = 16
BDF = 10
BEG = 18
The new critical path is:
BEG
and the minimum project duration becomes:
18 days
The original critical path is no longer critical.
📌 Key principle: A change to a non-critical activity can alter the entire project's critical path.
AQA-style amended network example
An AQA network-analysis question has used the following activity durations:
Activity | Original duration |
A | 6 days |
B | 4 days |
C | 8 days |
D | 4 days |
E | 4 days |
F | 2 days |
G | 7 days |
The three main routes are:
Route ACF
6 + 8 + 2 = 16 days
Route BDF
4 + 4 + 2 = 10 days
Route BEG
4 + 4 + 7 = 15 days
The original critical path is therefore:
ACF
with a duration of:
16 days
Now Activity E increases from:
4 days to 7 days
The amended BEG route becomes:
4 + 7 + 7 = 18 days
The revised routes are therefore:
Route | New duration |
ACF | 16 days |
BDF | 10 days |
BEG | 18 days |
The amended critical path becomes:
BEG
and the new project duration becomes:
18 days
This demonstrates exactly why network information needs to be recalculated rather than simply assuming the old critical path remains unchanged.
A systematic method for amending a network
When an activity duration changes, use the following process.
Step 1: Identify the activity that changed
Write down:
original duration
new duration
amount of change
For example:
E: 4 days → 7 days
Increase:
+3 days
Step 2: Identify the route or routes containing the activity
Trace the activity through the network.
For example:
Activity E lies on:
B → E → G
Step 3: Recalculate affected route durations
Do not assume the project duration changes by exactly the same amount as the activity.
Calculate the whole route again.
Step 4: Compare all routes
The longest valid route after the amendment becomes the critical path.
Step 5: Recalculate project duration
The duration of the new critical path becomes the revised minimum project completion time.
Step 6: Recalculate relevant node timings if required
If the network diagram itself needs to be updated, the earliest and latest timings may also change.
Step 7: Recalculate relevant float
A change to activity timing or overall project duration can alter the amount of float elsewhere in the network.
Step 8: Interpret the business consequence
Ask:
Has the project deadline changed?
Are different activities now critical?
Has management flexibility increased or decreased?
Should resources be reallocated?
Does management need to revise implementation decisions?
Recalculating earliest times
When activity durations change, the earliest possible time at which later events can occur may also change.
Earliest times are recalculated by working:
from left to right
through the network.
One route entering a node
Suppose a node can only be reached through Activity A.
Starting time:
0
Activity A:
6 days
Earliest time at next node:
0 + 6 = 6
Two routes entering the same node
Suppose a later node can only be reached after two incoming routes have been completed.
Route 1 arrives at:
12 days
Route 2 arrives at:
15 days
The earliest time at that node is:
15 days
because the project cannot move beyond the event until the required incoming work has been completed.
Therefore:
When several required routes enter a node, use the largest arrival time for the earliest event time.
This reflects the dependency.
Recalculating latest times
Latest timings are reconsidered by working:
from right to left
through the network.
Begin with the revised project completion time.
If the amended critical path changes project completion from:
16 days to 18 days
the final node becomes:
18
for the revised timing.
You can then work backwards through the network to identify how late earlier events can occur without delaying the revised project completion.
One activity leaving a node
Suppose:
final permissible time at next node = 18
Activity G takes 7 days
Latest permissible time at the preceding node:
18 - 7 = 11
More than one activity leaving a node
If several activities leave a node, management needs the timing that ensures all required routes can still be completed.
Use the earliest allowable result.
For example:
Route through Activity X allows the event to occur by day 12.
Route through Activity Y requires it by day 10.
The latest time for the node must therefore be:
10 days
Otherwise the route requiring completion by day 10 would be delayed.
Worked amended timing example
Return to the earlier network.
Original activities:
A = 6
B = 4
C = 8
D = 4
E = 4
F = 2
G = 7
Original project duration:
16 days
Activity E is changed to:
7 days
Forward calculation
Start:
0
After A:
0 + 6 = 6
After B:
0 + 4 = 4
Route through A and C:
6 + 8 = 14
Route through B and D:
4 + 4 = 8
The joining event before F therefore cannot occur before:
14
because the A-C route takes longer.
Route through B and amended E:
4 + 7 = 11
Then G:
11 + 7 = 18
Route through F:
14 + 2 = 16
Final completion therefore becomes:
18 days
The new critical route is:
B → E → G
Recalculating float after an amendment
Changing one activity can alter float elsewhere.
Recall the formula:
Total float = latest time at end node - activity duration - earliest time at start node
Suppose the revised network produces:
earliest start node for D = 4
D still takes 4 days
revised latest end-node time = 16
Then:
Total float for D = 16 - 4 - 4
= 8 days
The float for D has increased compared with its original six days.
Why?
Because the whole project now takes longer due to the changed route through E.
The deadline for completing the project has moved later, creating additional spare time on some other non-critical activities.
This demonstrates an important principle:
A delay can reduce float on one route while increasing float elsewhere because the overall project timetable has changed.
Recalculating float for the changed activity
Suppose E is now on the critical path.
Its total float will be:
0
because:
B → E → G
now determines the overall project duration.
Originally E was non-critical.
After the amendment, it becomes critical.
This means management priorities may need to change.
Float can disappear after an amendment
Suppose Activity H originally has:
4 days of float
Its duration increases by four days.
The entire float is used.
New float:
0 days
H may now be critical or lie on a critical route.
If H experiences any further delay:
no spare time remains → overall project completion is threatened
Management should therefore change how closely the activity is monitored.
Float may be reduced without disappearing
Suppose:
Original float:
6 days
Activity duration increases by:
2 days
Remaining float:
4 days
The project deadline need not change, but management has less flexibility.
Analytical chain:
Activity duration increases → some float is used → scheduling flexibility falls → future delays become more significant → activity may require closer monitoring.
This is more useful than simply saying:
The activity still has float.
Reassessing the critical path
Whenever activity timings change, ask:
What are the new route durations?
Which route is now longest?
Are two or more routes now equally long?
Has the project duration changed?
Which activities now have zero float?
Do not assume that the original critical path remains critical.
An amendment can create two critical paths
Suppose original routes are:
Route ACF = 20 days
Route BEG = 18 days
Critical path:
ACF
Now an activity on BEG increases by two days.
Revised routes:
ACF = 20
BEG = 20
There are now two critical paths.
This has important management consequences.
Before:
Only activities on ACF determine completion time
After:
Activities on both ACF and BEG determine completion time
This reduces scheduling flexibility.
A delay on either route could now delay the whole project.
An amendment can remove a critical path
Suppose a project originally has two critical paths of 20 days.
Management finds a way to reduce one route by three days.
The routes become:
Route ACF = 17 days
Route BEG = 20 days
Only:
BEG
remains critical.
Activities on ACF may now possess float.
This could increase management flexibility and change where resources are most urgently required.
When a critical activity becomes shorter
Changes are not always delays.
Suppose Activity C on the critical path is expected to take:
8 days
but managers discover that it will only take:
5 days
Original critical route:
A → C → F = 6 + 8 + 2 = 16
Revised:
A → C → F = 6 + 5 + 2 = 13
However, this does not automatically mean the entire project can finish in 13 days.
Another route may now be longer.
Suppose:
BEG = 15 days
After C is shortened:
ACF = 13 days
BEG = 15 days
The new critical path becomes:
BEG
The project duration falls only from:
16 days to 15 days
not to 13 days.
📌 Exam tip: Never calculate the effect of a changed critical activity in isolation. Compare the revised duration with all alternative routes.
How changes affect the minimum project completion time
There are several possibilities.
Outcome 1: Project duration increases
This may occur when:
a critical activity takes longer
a non-critical activity increases by more than its float
another route becomes the new longer critical route
Outcome 2: Project duration stays the same
This can occur when:
a non-critical activity is delayed by less than or equal to its float
For example:
4-day float + 3-day delay → overall completion unchanged
Outcome 3: Project duration decreases
This may occur if:
one or more critical activities are completed faster
no alternative route prevents the earlier completion
Outcome 4: Critical path changes but project duration does not
Suppose:
Original:
ACF = 16
BEG = 15
After ACF becomes one day shorter:
ACF = 15
BEG = 15
Project duration becomes 15 days, with both paths critical.
Alternatively, an adjustment could change which route is critical while maintaining the same total project duration depending on other route changes.
The important point is to recalculate the network rather than relying on assumptions.
Strategic significance of a changed critical path
A new critical path changes what management should treat as time-sensitive.
Suppose originally:
ACF is critical
Management prioritises Activities A, C and F.
After an amendment:
BEG becomes critical
Management may now need to prioritise:
B
E
G
This could affect:
allocation of employees
management attention
monitoring
communication
decisions about scarce resources
Therefore:
critical path changes → project priorities change → management decisions should also change
Resource allocation after an amendment
Suppose Activity E becomes critical.
Activity D now has substantial float.
Both require the same specialist employee.
Management might decide:
E is critical → delay would extend project completion → D has spare time → specialist employee moved from D to E → E receives priority → project deadline may be better protected.
However, this decision has a limitation.
If D is delayed too much:
float is used → D becomes critical → resource decision creates a new scheduling problem
Managers therefore need to consider the remaining float, not simply whether an activity is currently non-critical.
Amended networks and management attention
The network helps managers distinguish between activities that require different levels of attention.
Critical activity
Management may need:
frequent monitoring
rapid response to problems
priority access to scarce resources
Non-critical activity with little float
Still requires significant attention because a relatively small delay could make it critical.
Non-critical activity with substantial float
Management has more scheduling flexibility, although it should not be ignored.
The amendment can therefore change management priorities even when the actual tasks themselves remain unchanged.
Changes to deadlines
Strategic projects may have important deadlines.
For example:
opening a new facility
launching before a key selling period
entering a market before a competitor
implementing a new strategic system
Suppose a network amendment moves completion from:
20 weeks to 24 weeks
Managers must assess the consequence.
For example:
Project delayed by 4 weeks → planned market launch occurs after important sales period → expected revenue may fall → strategic value of project may be reduced.
The significance of a network amendment therefore depends on the business context.
A four-week delay is not equally important for every project.
Competitor actions can increase the significance of delays
Suppose two businesses are racing to introduce similar products.
Critical path increases → launch delayed → competitor enters market first → competitor may gain customers → strategic implementation becomes less valuable.
In this situation, managers might be willing to commit extra resources to critical activities.
In a project with no urgent competitive deadline, the same delay might be less significant.
Financial consequences of a network amendment
A longer project may create additional costs.
For example:
Project duration increases → employees and resources needed for longer → implementation costs may rise → expected return from strategy may fall.
However, management should not automatically attempt to reduce the delay at any cost.
Moving extra resources to critical activities can itself be expensive.
Managers therefore need to consider:
cost of delay versus cost of corrective action
Quality and timing
A network focuses heavily on timing.
Management should avoid sacrificing other strategic objectives simply to restore the original completion date.
For example:
Critical activity delayed → management rushes work → quality falls → strategic project is completed on time but performs poorly.
This means the fastest amended schedule is not automatically the best managerial choice.
Time must be considered alongside:
quality
cost
strategic objectives
Amendments and strategic implementation
AQA places network analysis within strategic implementation because strategies often need to be adjusted as actual events differ from plans.
Suppose a business is implementing a new production facility.
Original plan:
24 weeks
Unexpected delay:
Activity K takes 3 weeks longer
Network analysis can show whether:
the delay can be absorbed by float
the project duration changes
a new critical path emerges
Managers can then decide what action is required.
This is far more useful than simply knowing that "K is three weeks late".
Network amendments and leadership
An amended network provides information.
Managers still need leadership to decide how to respond.
For example:
New critical path identified → several activities now need additional attention → leader decides which resources to prioritise → revised implementation plan communicated.
This links to implementing strategy [Lesson 143. Implementing strategy].
Network analysis informs decisions. Leadership determines the response.
Network amendments and communication
When activity timings change, other teams may be affected.
For example:
Activity E delayed → Activity G cannot start at planned time → employees responsible for G need revised information → schedules and resources may need to change.
Poor communication could mean:
network updated centrally → affected employees are not informed → teams continue following old timetable → disruption increases.
Amending the diagram therefore creates little value unless revised information reaches the relevant people.
Network amendments and organisational structure
Managers may need to react quickly when critical activities change.
If the organisational structure creates slow approval processes:
critical activity develops problem → local manager identifies solution → senior approval required → response delayed → project falls further behind.
A suitable organisational structure can therefore affect how effectively network information is used.
This connects with organisational structure and implementation [Lesson 144. Organisational structure and implementation].
Network analysis does not remove uncertainty
Updating the network improves the plan using the latest information.
It does not guarantee that no further changes will occur.
For example:
E revised from 4 days to 7 days → network amended → later G also experiences delay → network must be reconsidered again.
Network analysis is therefore an ongoing management tool.
Managers should be prepared to update the project as implementation develops.
The value of continually updating a network
More accurate project information
The network reflects current expectations rather than outdated estimates.
Better identification of priorities
Managers can identify the activities that are currently critical.
More effective resource decisions
Resources can be directed according to revised float and critical-path information.
Better monitoring
Management can compare actual progress with the latest project plan.
Improved response to change
The organisation can adjust implementation rather than continuing to follow a plan that is no longer realistic.
These benefits connect network analysis with the wider idea of organisational flexibility.
Limitations of amending the network
Revised timings are still estimates
A revised duration may also prove inaccurate.
Frequent changes can create complexity
If several activities keep changing, managers may need to amend the network repeatedly.
Changing the diagram does not solve the cause of delay
For example:
Specialist employee unavailable → network amended → employee remains unavailable
The diagram reflects the problem but does not remove it.
Resources may prevent corrective action
Management may know that a critical activity needs additional resources but lack the finance, labour or equipment required.
Other implementation factors remain important
Strategic implementation still depends on:
leadership
communication
organisational structure
employee cooperation
An accurate amended network is only one management tool.
Interpreting a delay using float
When an activity is delayed, compare:
size of delay with total float
Example 1
Float:
5 days
Delay:
2 days
Result:
2 < 5
Project completion does not have to change.
Remaining float:
3 days
Example 2
Float:
5 days
Delay:
5 days
Result:
All float is used.
Project completion can remain unchanged, but the activity now has no spare time.
Example 3
Float:
5 days
Delay:
8 days
Excess delay:
8 - 5 = 3 days
The route is now three days beyond its previous allowable timing.
Managers must recalculate the network to see whether:
project duration increases
a new critical path emerges
Do not use float mechanically
A useful shortcut is:
delay less than float → project deadline unaffected
but always remember that network timings can interact.
For larger or more complex amendments, recalculate the routes and relevant node timings.
The safest examination method is:
calculate the size of the change
compare it with float
recalculate the affected route
compare it with other routes
Worked example: delay within float
A project has:
Critical path ACF = 22 days
Another route:
BDG = 18 days
An activity on BDG is delayed by:
3 days
New route:
18 + 3 = 21 days
Comparison:
ACF = 22
BDG = 21
The critical path remains:
ACF
Project duration remains:
22 days
The delay has been absorbed by spare time.
Worked example: delay creates equal critical paths
Original:
ACF = 22
BDG = 18
Activity on BDG delayed by:
4 days
New route:
22 days
Now:
ACF = 22
BDG = 22
There are two critical paths.
Project duration remains:
22 days
However, management flexibility has decreased.
Previously BDG had four days of spare time.
Now it has none.
Worked example: delay creates a longer project
Original:
ACF = 22
BDG = 18
Activity on BDG delayed by:
6 days
New route:
24 days
Now:
ACF = 22
BDG = 24
New critical path:
BDG
New project duration:
24 days
Project completion has been delayed by:
2 days
Notice that the activity itself was delayed by six days, but the project was delayed by only two because the route originally contained four days of spare time.
This is a crucial interpretation skill.
Worked example: activity completed early
Original routes:
ACF = 20
BEG = 18
ACF is critical.
Suppose critical Activity C is completed:
3 days faster
New ACF:
17 days
Now compare:
ACF = 17
BEG = 18
New critical path:
BEG
New project duration:
18 days
The critical activity improved by three days, but the total project duration improved by only:
2 days
because another route now determines completion.
Recalculate rather than assume
These examples demonstrate why common shortcuts can fail.
Wrong assumption
A critical activity becomes three days faster, so the project becomes three days faster.
Not necessarily.
Correct approach
Change activity duration → recalculate its route → compare all routes → identify new critical path → determine revised completion time
Likewise:
Wrong assumption
A non-critical activity is delayed, so the project is delayed.
Not necessarily.
The activity may have sufficient float.
Management decisions following an amendment
Managers may respond in several ways depending on the revised information.
Continue without action
Appropriate where:
delay is within available float
project completion remains unaffected
Increase monitoring
Appropriate where:
most float has been used
activity is close to becoming critical
Reallocate resources
Appropriate where:
a newly critical activity requires support
other activities possess sufficient float
Revise the project timetable
Necessary where:
completion date has genuinely changed
the original timetable is no longer realistic
Communicate the change
Affected employees and managers need to understand the revised timings.
The network identifies what has changed. Management must then act on it.
Should managers always try to restore the original deadline?
No.
Suppose restoring the deadline requires substantial additional expenditure.
Managers need to compare:
cost of late completion
with
cost of speeding up implementation
For example:
Situation A
A two-week delay means missing an important seasonal sales period.
The cost of delay may be substantial.
Management may justify extra spending.
Situation B
A two-week delay creates little effect on customers or revenue.
Expensive corrective action may not be worthwhile.
The network provides timing information, but managerial judgement remains essential.
Using amended network information in evaluation
A strong evaluative answer should consider:
how much the timing changed
whether the activity was originally critical
available float
whether the critical path changed
urgency of project completion
availability and cost of resources
strategic consequences of delay
For example:
The three-day increase in Activity E is strategically significant because it changes the critical path and moves project completion from 16 to 18 days. If the project has a fixed launch deadline, management may need to prioritise resources towards E and G. If the deadline is flexible, accepting the additional two days may be less costly than reallocating scarce resources.
This is much stronger than:
The delay is bad because the project takes longer.
How to answer an AQA network-amendment question
For a one-mark question
Give the answer directly.
For example:
New critical path = BEG
For a duration question
Show the route calculation if space permits:
B + E + G = 4 + 7 + 7 = 18 days
For float
Write:
Total float = latest end time - duration - earliest start time
Then substitute the figures.
For an analyse question
Use the network information in a chain:
Activity duration increases → available float is used → activity becomes critical → management has no spare time for further delay → closer monitoring may be required → strategic deadline is more vulnerable
For evaluation
Add context:
How urgent is completion?
Is the delay costly?
Can resources be moved?
Are activity estimates reliable?
Does the critical path change?
📌 Exam tip: Always recalculate before explaining the business consequence. If the network calculation is wrong, the rest of the analysis may be based on an incorrect project position.
Key Words 🔑
Key word | Student-friendly definition | How it may be used in an exam |
Amended network | A network diagram or project analysis updated to reflect changed activity information. | Recalculate timings, critical paths and float when project information changes. |
Critical path | The sequence of activities determining the minimum project completion time. | Reassess which route becomes critical after an activity duration changes. |
Total float | The amount of time an activity can be delayed without delaying overall project completion, assuming other timings remain unchanged. | Assess how much of a delay can be absorbed before the project timetable is threatened. |
Activity duration | The expected time required to complete a project activity. | Replace the original timing with revised information and recalculate the network. |
Project duration | The minimum completion time determined by the current critical path. | Compare the original and revised completion times after an amendment. |
Common Mistakes ⚠️
Mistake: Adding the entire activity delay to the project duration
Why this is incorrect: A non-critical activity may have float that absorbs some or all of the delay.
How to improve: Compare the activity's delay with its float and recalculate the route.
Mistake: Keeping the original critical path automatically
Why this is incorrect: Another route may become longer after an amendment.
How to improve: Recalculate every affected route and compare it with the existing critical route.
Mistake: Assuming a change to a critical activity changes the project by exactly the same amount
Why this is incorrect: Another route can become the new critical path.
How to improve: Always compare the revised route against the alternative routes.
Mistake: Assuming a non-critical activity cannot become critical
Why this is incorrect: A sufficiently large increase in its duration can use all available float and create a new critical path.
How to improve: Reassess the whole network after the timing changes.
Mistake: Forgetting that float itself can change
Why this is incorrect: Changing the project duration or node timings can alter float elsewhere in the network.
How to improve: Recalculate relevant float using the revised timings.
Mistake: Treating an activity delayed by exactly its float as immediately delaying the project
Why this is incorrect: The activity can use all of its float without necessarily delaying overall completion.
How to improve: Recognise that it now has zero float, making any further delay particularly significant.
Mistake: Focusing only on the arithmetic
Why this is incorrect: Network analysis is included within strategic implementation.
How to improve: Explain how revised information affects:
resources
monitoring
project deadlines
implementation decisions
Mistake: Assuming an amended network solves the delay
Why this is incorrect: The network identifies and measures the effect. Managers still need to decide how to respond.
How to improve: Separate:
project information
from
management action
Exam-Style Questions ✍️
Question 1
A project originally has the following routes:
ACF = 19 days
BDG = 17 days
Activity D now takes 3 days longer.
Calculate the revised duration of BDG and identify the new critical path. [2 marks]
Question 2
Activity K has 5 days of total float. It is now expected to take 3 days longer than originally planned.
Calculate the amount of float remaining. [2 marks]
Question 3
An activity has 4 days of total float and is delayed by exactly 4 days.
Explain the implication for the project. [3 marks]
Question 4
A critical activity originally takes 7 days but is now expected to take 10 days.
Explain why management should not automatically assume that the total project duration will increase by exactly 3 days. [3 marks]
Question 5
A project contains these routes:
Route | Original duration |
ACF | 21 days |
BDG | 16 days |
BEH | 19 days |
Activity E lies on route BEH and is now expected to take 4 days longer.
a) Calculate the revised duration of BEH. [1 mark]
b) Identify the new critical path or paths. [1 mark]
c) State the revised minimum project duration. [1 mark]
Question 6
Northstar Ltd
Northstar Ltd is implementing a new distribution strategy.
Activity F originally had six days of total float. It is now expected to take four days longer.
Analyse the implications of this change for Northstar Ltd's project management. [9 marks]
Question 7
VisionTech plc
VisionTech plc is implementing a new digital production system.
Its original network contained:
critical path ACF = 24 weeks
route BEG = 21 weeks
An unexpected problem means an activity on BEG will now take five weeks longer.
The project must be completed before the start of VisionTech's busiest selling period.
Analyse the implications of the change for VisionTech plc's strategic implementation. [9 marks]
Question 8
Harbour Foods Ltd
Harbour Foods Ltd is implementing a strategic project to open a new production facility.
The original project had a minimum duration of 30 weeks.
During implementation:
an activity with significant float has been delayed
another activity is now expected to take longer than planned
management believes the critical path may have changed
specialist employees can be moved between activities, but doing so increases costs
a competitor is planning to open a similar facility
Evaluate the importance of continually amending the network diagram during Harbour Foods Ltd's strategic implementation. [16 marks]
Answers and indicative mark scheme
Question 1
Original BDG:
17 days
Activity D increases by:
3 days
Revised BDG:
17 + 3 = 20 days
Compare:
ACF = 19
BDG = 20
Therefore:
New critical path = BDG
New project duration = 20 days
Question 2
Original float:
5 days
Increase in activity duration:
3 days
Remaining float:
5 - 3 = 2 days
Answer: 2 days
Question 3
The activity uses all four days of its available float.
Therefore:
4-day delay = 4-day float
The overall project completion date need not change, assuming other timings remain unchanged.
However, the activity now has:
0 days float
Any further delay could therefore threaten the project's completion time.
Question 4
The critical route containing the activity becomes three days longer, but another route may become critical.
For example:
critical route becomes longer or shorter relative to alternative routes → another path may determine completion → total project duration must be found by recalculating and comparing all routes.
Management should therefore revise the whole network rather than simply adding three days to the previous project duration.
Question 5
Original BEH:
19 days
E takes:
4 days longer
a)
Revised BEH:
19 + 4 = 23 days
b)
Compare:
ACF = 21
BDG = 16
BEH = 23
New critical path = BEH
c)
Revised project duration = 23 days
Question 6
Activity F originally has six days of float.
It is expected to take four days longer.
Therefore:
4-day increase < 6-day float
The increase can potentially be absorbed without delaying Northstar's overall project.
Remaining float becomes:
6 - 4 = 2 days
This means the change is not currently enough to alter project completion, assuming other timings remain unchanged.
However, F now has much less scheduling flexibility.
A possible analytical chain is:
Activity takes four days longer → most of its float is used → only two days spare time remain → further delays become more significant → management may need to monitor F more closely.
Northstar may therefore avoid an immediate expensive response because the project deadline has not yet changed.
However, ignoring F completely could be risky because another delay of more than two days could make the route critical.
Question 7
Original routes:
ACF = 24 weeks
BEG = 21 weeks
An activity on BEG takes:
5 weeks longer
New BEG:
21 + 5 = 26 weeks
The new critical path therefore becomes:
BEG
and project duration increases from:
24 weeks to 26 weeks
This means VisionTech's project is now expected to take two weeks longer overall.
The difference matters because completion must occur before its busiest selling period.
A possible chain is:
New critical path = 26 weeks → project completion delayed by two weeks → production system may not be operational for busiest period → VisionTech could have less capacity or efficiency when demand is highest → potential sales or profit may be affected.
Management may therefore consider reallocating resources towards critical activities.
However:
Additional resources used → implementation cost rises → financial benefit of completing sooner may be reduced.
The best decision depends on how valuable the busy selling period is compared with the cost of restoring the timetable.
Question 8
Continually amending the network could be highly valuable because Harbour's original 30-week plan is becoming outdated.
One activity has already been delayed and another duration has changed.
Therefore:
original timings become inaccurate → original critical path may no longer determine completion → managers could prioritise the wrong activities unless the network is updated.
Amending the network enables Harbour to:
identify the new critical path
calculate the revised project duration
recalculate relevant float
identify activities that now require closer monitoring
make better-informed resource decisions
This is particularly useful because specialist employees can be moved between activities.
For example:
New critical activity identified → non-critical activity retains float → specialist employee can be moved towards critical activity → delay may be reduced → opening date may be protected.
The competitor increases the strategic importance of timing.
Harbour opens late → competitor may open first → competitor could establish customer relationships earlier → strategic value of Harbour's project may fall.
However, continually updating the network has limitations.
Activity timings remain estimates. Another unexpected change could make the revised network inaccurate again.
Moving specialist employees also increases costs.
Network identifies opportunity to accelerate project → resources moved → implementation cost rises → profitability of strategy may fall.
Harbour must therefore consider whether the benefit of earlier completion outweighs the extra cost.
The network also does not solve underlying implementation problems. Successful implementation still depends on factors such as:
leadership
communication
availability of resources
employee cooperation
Evaluation:
Continual amendment is likely to be particularly important for Harbour because the project environment is already changing and timing has strategic significance due to the competitor.
Using the original network after activity durations have changed could lead management to monitor the wrong activities and misunderstand the true completion date.
However, the value comes from using the revised information to make sensible decisions, not from repeatedly redrawing the network for its own sake.
Harbour should therefore update the network whenever a change is significant enough to affect route durations, float or the critical path, and then compare the strategic value of protecting the project deadline with the costs of corrective action.