Critical Path Analysis | Edexcel A-Level Business

Sep 24
21 min read

Updated: 13 hours ago


For Specification 9BS0


Pearson Edexcel A-Level Business | Free Revision Notes


Estimated study time: 60 minutes



Critical Path Analysis A-Level Business revision focuses on planning and managing projects made up of several interdependent activities. Edexcel requires you to understand the nature and purpose of Critical Path Analysis (CPA), complete and interpret simple networks, identify the critical path and calculate Earliest Start Time, Latest Finish Time and total float. CPA completes the decision-making techniques section after decision trees [Lesson 53. 3.3.3 Decision trees] and investment appraisal [Lesson 52. 3.3.2 Investment appraisal].


Learning Objectives 🎯


By the end of this revision page, you should be able to:

  • Explain the nature and purpose of Critical Path Analysis.

  • Complete and interpret simple network diagrams.

  • Calculate Earliest Start Times (ESTs).

  • Calculate Latest Finish Times (LFTs).

  • Identify the critical path through a network.

  • Calculate and interpret total float.

  • Analyse the usefulness and limitations of Critical Path Analysis.


Revision Notes 📚


What is Critical Path Analysis?


Critical Path Analysis (CPA) is a project-planning technique used to organise the sequence and timing of activities required to complete a project.


In the 2021 Edexcel mark scheme, CPA was described as planning the sequence of activities in a project so that the quickest and most efficient way of completing it can be identified while ensuring that all stages are completed.


CPA is therefore useful when a project contains several activities that:

  • take different lengths of time

  • must happen in a particular sequence

  • can sometimes take place simultaneously

  • depend on other activities being completed first


Examples of business projects might include:

  • installing a new IT system

  • opening a new facility

  • introducing new equipment

  • completing a major business project


The specification focuses on the planning and interpretation of simple networks, rather than wider project-management techniques.


The Purpose of Critical Path Analysis


CPA helps managers answer several important questions:

  • What activities need to be completed?

  • In what order must they take place?

  • Which activities can happen at the same time?

  • What is the minimum time required to complete the whole project?

  • Which activities cannot be delayed without delaying the entire project?

  • Which activities have some spare time available?


The 2021 Edexcel assessment showed these uses in the context of Buy it Direct's installation of a new warehouse IT system. CPA indicated that the project could be completed in 41 weeks, four weeks before its 45-week target.


This demonstrates the core value:


activities planned in sequence → project completion time identified → managers can compare completion time with deadline


Understanding a Network Diagram


Activities


An activity is a task that must be completed as part of a project.


Each activity has a duration.


For example:

Activity

Task

Duration

A

Design new store layout

3 weeks

B

Order equipment

5 weeks

C

Prepare premises

4 weeks


Activities are connected according to the order in which they must happen.


Events


The points connecting activities represent stages in the project.


A network begins at a starting event and ends when the project is complete.


A simple network might look like this:

                A, 3 weeks             C, 4 weeks
          (1) ───────────→ (2) ───────────→ (4)
            \                                \
             \ B, 5 weeks                     \ E, 2 weeks
              \                                \
               └──────────→ (3) ───────────→ (5)
                             D, 3 weeks

A clearer representation of the relationships is:

(1) ──A 3──> (2) ──C 4──> (4) ──E 2──> (5)
  \
   └─B 5──> (3) ──D 3────> (4)

This network contains two possible routes from the beginning to completion:


A → C → E


and


B → D → E


The activities do not all need to take place one after another. Some may take place at the same time.


Earliest Start Time


What is Earliest Start Time?


Earliest Start Time (EST) identifies the earliest point at which an activity or stage of the project can begin, given the activities that must already have been completed.


The starting point of a project normally has an EST of:


$$

0

$$


To calculate ESTs, work through the network from left to right.


This is often called working forwards through the network.


Calculating EST when there is one preceding route


Using this activity:

(1) ──A 3──> (2)

If the EST at node 1 is:


$$

0

$$


and activity A takes:


$$

3

$$


weeks, then the earliest node 2 can be reached is:


$$

0+3=3

$$


Therefore:


$$

\boxed{\text{EST at node 2}=3}

$$


What happens when routes meet?


This is one of the most important rules in CPA.


Suppose two activities must both be completed before the project can continue.


If one route reaches the node after 7 weeks and another reaches it after 8 weeks, the next activity cannot begin at week 7.


It must wait until both routes are complete.


Therefore you take the largest number.


For example:


Route 1:


$$

3+4=7

$$


Route 2:


$$

5+3=8

$$


The EST of the joining node is:


$$

\boxed{8}

$$


Forward-pass rule


When two or more routes meet:


Use the highest possible EST.

The project must wait for the slowest preceding route to be completed.


Worked Example: Calculating EST


Use the following network:

(1) ──A 3──> (2) ──C 4──> (4) ──E 2──> (5)
  \
   └─B 5──> (3) ──D 3────> (4)

Node 1


Starting point:


$$

\boxed{EST=0}

$$


Node 2


$$

0+3=3

$$


Therefore:


$$

\boxed{EST=3}

$$


Node 3


$$

0+5=5

$$


Therefore:


$$

\boxed{EST=5}

$$


Node 4


Two routes enter node 4.


Through A and C:


$$

3+4=7

$$


Through B and D:


$$

5+3=8

$$


Take the larger figure:


$$

\boxed{EST=8}

$$


Node 5


Activity E lasts 2 weeks:


$$

8+2=10

$$


Therefore:


$$

\boxed{EST=10}

$$


The minimum project completion time is therefore:


$$

\boxed{10\text{ weeks}}

$$


Latest Finish Time


What is Latest Finish Time?


Latest Finish Time (LFT) identifies the latest point by which an activity or stage must be completed without delaying the overall project.


To calculate LFTs:

  1. Begin at the final event.

  2. Set the final LFT equal to the project's completion time.

  3. Work backwards, from right to left.

  4. Subtract activity durations.


Starting the backward calculation


In the worked example, the earliest possible completion time is:


$$

10\text{ weeks}

$$


Therefore the final event has:


$$

\boxed{LFT=10}

$$


Calculating backwards


From node 5 to node 4, activity E lasts 2 weeks.


Therefore:


$$

10-2=8

$$


So:


$$

\boxed{LFT\text{ at node 4}=8}

$$


What happens when routes split?


When working backwards, there may be more than one route leaving an earlier event.


The project must satisfy all of the later timing requirements.


Therefore, use the smallest possible LFT.


Backward-pass rule


When more than one route must be considered:


Use the lowest possible LFT.

This ensures no following activity is delayed.


Worked Example: Calculating LFT


Continue with:

(1) ──A 3──> (2) ──C 4──> (4) ──E 2──> (5)
  \
   └─B 5──> (3) ──D 3────> (4)

We already know:


$$

LFT_5=10

$$


Node 4


$$

10-2=8

$$


Therefore:


$$

\boxed{LFT_4=8}

$$


Node 2


Activity C takes 4 weeks:


$$

8-4=4

$$


Therefore:


$$

\boxed{LFT_2=4}

$$


Node 3


Activity D takes 3 weeks:


$$8-3=5$$


Therefore:


$$\boxed{LFT_3=5}$$


Node 1


There are two routes.


Through A:


$$

4-3=1

$$


Through B:


$$

5-5=0

$$


Take the smaller figure:


$$

\boxed{LFT_1=0}

$$


The completed EST and LFT information is:

Node

EST

LFT

1

0

0

2

3

4

3

5

5

4

8

8

5

10

10


The Critical Path


What is the critical path?


The critical path is the sequence of activities that determines the minimum time required to complete the whole project.


Activities on the critical path cannot be delayed without delaying the project's completion, unless the lost time is recovered elsewhere on that path.


The 2021 Buy it Direct network had a critical path consisting of activities:


$$

\boxed{C \rightarrow D \rightarrow F \rightarrow G}

$$


and a total project duration of 41 weeks.


Identifying the critical path using route lengths


In our worked example:


Route 1


$$

A+C+E

$$


9\text{ weeks}

$$


Route 2


$$

B+D+E

$$


10\text{ weeks}

$$


The longest route is:


$$

\boxed{B \rightarrow D \rightarrow E}

$$


Therefore this is the critical path.


The minimum project completion time is:


$$

\boxed{10\text{ weeks}}

$$


Why is the longest route critical?


It may seem strange that the business wants to identify the longest route when CPA is intended to help complete a project quickly.


The reason is that the longest necessary sequence controls how quickly the whole project can be completed.


Other routes finish earlier and therefore have some spare time.


The critical route does not.


So:


longest necessary route through network → determines minimum completion time → critical path


Total Float


What is total float?


Total float is the amount of time by which a non-critical activity can be delayed without delaying the overall completion of the project.


The formula supported by Edexcel's 2021 mark scheme is:


\text{LFT at end of activity}


\text{duration}


\text{EST at start of activity}}

$$


For example, Edexcel calculated the float of one Buy it Direct activity as:


$$

18-2-0=16\text{ weeks}

$$


A total float of 16 weeks means that this activity could be delayed by up to 16 weeks without delaying the overall project, assuming the rest of the network proceeds according to plan.


Worked Example: Total Float


Using our network:

Activity

Start EST

Duration

End LFT

A

0

3

4

B

0

5

5

C

3

4

8

D

5

3

8

E

8

2

10


Activity A


$$

4-3-0=1

$$


Therefore:


$$

\boxed{\text{Float of A}=1\text{ week}}

$$


Activity B


$$

5-5-0=0

$$


Therefore:


$$

\boxed{\text{Float of B}=0}

$$


Activity C


$$

8-4-3=1

$$


Therefore:


$$

\boxed{\text{Float of C}=1\text{ week}}

$$


Activity D


$$

8-3-5=0

$$


Therefore:


$$

\boxed{\text{Float of D}=0}

$$


Activity E


$$

10-2-8=0

$$


Therefore:


$$

\boxed{\text{Float of E}=0}

$$


The final results are:

Activity

Duration

Total float

Critical?

A

3

1

No

B

5

0

Yes

C

4

1

No

D

3

0

Yes

E

2

0

Yes


Therefore the critical path is:


$$

\boxed{B \rightarrow D \rightarrow E}

$$


Zero Float and Critical Activities


Activities on the critical path have:


$$

\boxed{\text{total float}=0}

$$


This means there is no spare time available.


For example:


Activity D delayed by 1 week → critical path becomes 1 week longer → entire project finishes 1 week later


By contrast, Activity A has one week of float:


Activity A delayed by 1 week → project can still finish in 10 weeks


But:


Activity A delayed by 2 weeks → available float exceeded → overall project may be delayed


A Quick CPA Calculation Method


Forward pass for EST


Work:


$$

\boxed{\text{left to right}}

$$


  • Start with 0.

  • Add activity durations.

  • When paths meet, select the highest value.


Memory rule


EST = go forwards and take the greatest.


Backward pass for LFT


Work:


$$

\boxed{\text{right to left}}

$$


  • Start with the final project duration.

  • Subtract activity durations.

  • When paths split, select the lowest value.


Memory rule


LFT = go backwards and take the lowest.


Float


Use:


\text{end LFT}


\text{duration}


\text{start EST}}

$$


Critical path


Look for activities with:


$$

\boxed{\text{zero total float}}

$$


and confirm that they form the route determining the total project duration.


Interpreting CPA Information


A calculation is only useful if you can explain what it means.


Suppose CPA shows:

  • total project time = 30 weeks

  • deadline = 35 weeks

  • activity A float = 4 weeks

  • activities C, E and F are critical


You could interpret this as:


The project is planned to finish five weeks before the deadline. Activity A could be delayed by up to four weeks without delaying the overall project. However, activities C, E and F require particularly close management because they have no total float.

This turns the numerical information into a business interpretation.


Why is Identifying the Critical Path Useful?


The critical path tells managers which activities require the closest attention.


If a critical activity is delayed:


critical activity delayed → following critical activities begin later → overall project completion delayed


Managers may therefore focus monitoring and resources on critical activities.


In Buy it Direct's project, Edexcel identified activities C, D, F and G as critical.


Knowing this could help managers focus particularly closely on those stages of the IT installation.


Why is Float Useful?


Float identifies flexibility within the project.


Suppose:

  • Activity A has 5 weeks of float.

  • Activity B is critical.


Managers may have more flexibility in when Activity A is completed.


This could help them manage:

  • employees

  • equipment

  • finance

  • the timing of other activities


In the Buy it Direct network, Edexcel calculated 16 weeks of float for activities A, B and E.


This showed that these activities had considerable flexibility compared with the critical activities.


CPA and Simultaneous Activities


One advantage of a network diagram is that it can show that some activities do not have to wait for unrelated activities to finish.


Different tasks may be completed at the same time where the network allows.


Edexcel's 2021 mark scheme recognised this as a benefit because CPA enabled Buy it Direct to schedule project activities simultaneously and calculate a 41-week completion time.


The potential chain is:


activities scheduled simultaneously → unnecessary waiting reduced → project completed sooner → deadline more likely to be achieved


CPA and Deadlines


CPA allows the business to compare its calculated project duration with a deadline.


For Buy it Direct:

  • required completion = 45 weeks

  • CPA completion time = 41 weeks


Difference:


$$

45-41=4\text{ weeks}

$$


CPA therefore indicated the project should finish:


$$

\boxed{4\text{ weeks before the deadline}}

$$


This is valuable information because managers can see whether the planned sequence is capable of meeting the objective before implementation begins.


CPA and Resource Planning


Once managers understand which activities are critical and which contain float, they may be able to organise resources more effectively.


For example:


non-critical activity has float → some flexibility exists in its timing → resources may be concentrated temporarily on a critical activity


The objective is not simply to make every task finish as quickly as possible.


Instead, managers can concentrate particularly on ensuring the whole project remains on schedule.


CPA and Cash-Flow Management


The 2021 Edexcel mark scheme specifically identified improved cash-flow management as a possible value of CPA.


In the Buy it Direct project, the timing information meant equipment suppliers did not need to be paid until week 23.


The chain is:


timing of activity identified → business knows when expenditure is likely to be required → cash outflows can be planned more effectively


This demonstrates why float and timing information can have financial as well as operational value.


Critical Path Analysis and Business Decision-Making


CPA is one of several quantitative decision-making techniques in Theme 3.


It follows:

  • quantitative sales forecasting [Lesson 51. 3.3.1 Quantitative sales forecasting]

  • investment appraisal [Lesson 52. 3.3.2 Investment appraisal]

  • decision trees [Lesson 53. 3.3.3 Decision trees]


Each answers a different type of question.

Technique

Main purpose

Quantitative sales forecasting

Estimate future sales using numerical data

Investment appraisal

Assess potential investments financially

Decision trees

Compare uncertain decisions using probabilities and outcomes

Critical Path Analysis

Plan the sequence and timing of a project


CPA therefore focuses on project timing and sequencing, rather than forecasting sales or estimating investment returns.


Limitations of Critical Path Analysis


Activity times may be inaccurate


CPA depends on estimated durations.


If these estimates are wrong, the calculated project duration may also be wrong.


This was a major limitation identified in the 2021 Edexcel mark scheme. Buy it Direct's Operations Director was new and might lack sufficient experience, meaning activities could take longer than the estimated times.


Possible chain:


activity duration underestimated → ESTs and LFTs based on inaccurate figure → project actually takes longer → planned completion date becomes unreliable


A perfectly completed network cannot compensate for poor data.


Unexpected events may disrupt the network


Business projects do not always proceed exactly as planned.


Edexcel gave the example of possible teething problems with Buy it Direct's new equipment.


If an unexpected problem affects a critical activity:


critical activity delayed → no float available → project completion may be delayed


Even non-critical activities can become problematic if delays exceed their available float.


This links to the uncertainty businesses face from external influences [Lesson 46. 3.1.4 Impact of external influences].


CPA may encourage too much focus on speed


Completing a project quickly is not always the only objective.


The 2021 mark scheme warned that CPA could cause managers to focus excessively on speed rather than quality. In the Buy it Direct context, insufficient time for staff training could reduce the effectiveness of the project.


Possible chain:


focus on meeting critical timings → activity rushed → quality of implementation falls → project may finish on time but perform poorly


Therefore:


Fastest completion does not automatically mean best project outcome.

CPA is a planning tool


A network diagram represents the plan.


It cannot ensure that employees, suppliers or equipment actually perform exactly as expected.


Edexcel's judgement on Buy it Direct emphasised that the value of CPA depended on the actual implementation of activities. Staff recruitment or training could take longer than planned, making CPA only a planning tool rather than a guarantee.


The distinction is:


CPA can identify what should happen


but


management still has to make it happen


A critical activity can still go wrong


Identifying an activity as critical tells managers it needs attention.


It does not prevent delays.


For example:


critical activity identified → manager monitors activity closely


may reduce risk, but unexpected difficulties can still occur.


CPA manages information about timing rather than eliminating operational uncertainty.


Float is not an invitation to delay activities unnecessarily


An activity with 10 weeks of float could theoretically be delayed within the timing constraints of the network.


That does not automatically mean managers should delay it by 10 weeks.


Unexpected future problems could use some of that flexibility.


Float should therefore be interpreted as available scheduling flexibility, not spare time that must be used.


Assessing the Usefulness of CPA


When an exam asks about the value or usefulness of CPA, do not simply describe the network.


Instead, explain what the information allows the business to do.


Useful argument


CPA shows that the project can be completed in 30 weeks against a 34-week deadline. This gives managers evidence that the planned sequence is capable of meeting the deadline, while allowing them to focus closely on activities with zero float.

Limitation


However, the 30-week figure depends on the activity-duration estimates being accurate. If installation takes longer than expected, the calculated completion date may no longer be achievable.

Supported judgement


CPA is therefore likely to be useful as a planning and monitoring tool, but its value depends on reliable estimates and effective implementation of the activities.

This is much stronger than writing:


"CPA shows the critical path and float."

A Real Edexcel Example: Buy it Direct


The 2021 examination provides an excellent model of how CPA may appear in an extended question.


Buy it Direct planned to install a new IT system in its warehouses. The project had to be completed within 45 weeks.


The network showed:

  • planned completion time = 41 weeks

  • deadline = 45 weeks

  • critical path = C, D, F, G

  • float on A = 16 weeks

  • float on B = 16 weeks

  • float on E = 16 weeks


Value


CPA could help the business:

  • identify that the project should meet the deadline

  • identify the activities that cannot be delayed

  • identify flexibility in non-critical activities

  • plan the timing of cash outflows

  • schedule activities simultaneously


Limitations


However:

  • activity times could be inaccurate

  • unexpected problems could occur

  • managers might prioritise speed over quality

  • successful implementation still depends on actually completing activities as planned


The mark scheme therefore supported a balanced assessment, not the view that CPA automatically guarantees successful project management.


CPA and Evidence-Based Decision-Making


CPA generates numerical evidence that managers can use when planning.


For example:

  • project duration

  • ESTs

  • LFTs

  • float

  • critical activities


However, managers still need judgement when interpreting this information.


This provides a useful link to corporate influences [Lesson 55. 3.4.1 Corporate influences], where you will consider evidence-based and subjective decision-making.


A manager might have accurate CPA figures but still need to decide:

  • where extra attention is required

  • whether timing estimates are realistic

  • whether quality is being sacrificed

  • how to respond when the project changes


CPA Calculation Summary


Earliest Start Time


Work forwards.


At a joining point:


$$

\boxed{\text{choose the highest value}}

$$


Latest Finish Time


Work backwards.


At a splitting point:


$$

\boxed{\text{choose the lowest value}}

$$


Total Float


\text{LFT at end}


\text{activity duration}


\text{EST at start}}

$$


Critical Path


The critical path:

  • determines the minimum project duration

  • consists of critical activities

  • has zero total float


CPA Exam Checklist


Before finishing a CPA question, check:

  1. Have I worked EST forwards?

  2. At joining nodes, have I used the largest figure?

  3. Have I worked LFT backwards?

  4. At splitting points, have I used the smallest figure?

  5. Have I used the correct duration for each activity?

  6. Have I calculated total float using the correct start EST and end LFT?

  7. Have I identified the continuous route of zero-float activities?

  8. Have I stated the total project duration?

  9. If the question asks for value or usefulness, have I explained what the figures mean for the business?

  10. Have I considered limitations rather than assuming the network is perfectly accurate?


Key Words 🔑

Key word

Student-friendly definition

How it may be used in an exam

Critical Path Analysis (CPA)

A technique for planning the sequence and timing of activities in a project to identify the quickest completion route.

Explain or assess how CPA may help a business manage a project.

Critical path

The sequence of activities that determines the minimum time needed to complete the project.

Identify the route of zero-float activities and calculate total project duration.

Earliest Start Time (EST)

The earliest time at which an activity or stage can begin given the activities before it.

Complete a network by working forwards through activity durations.

Latest Finish Time (LFT)

The latest point by which an activity or stage must be completed without delaying the project.

Complete a network by working backwards from the project completion time.

Total float

The time by which an activity can be delayed without delaying the overall project.

Calculate scheduling flexibility and identify critical activities.


Hints from the Examiner Reports 💡


The November 2021 examiner report found that CPA was only vaguely understood by the majority of candidates, and a significant number did not attempt the question at all.


Examiner hint: CPA is an area where secure knowledge of the underlying concepts matters. Learn what the critical path, float, EST and LFT actually tell managers rather than relying on vague comments about "planning".

Many candidates simply described the network diagram without explaining the value of CPA to the business.


Examiner hint: If the question asks about the value of CPA, use the numbers. Explain why the project duration, deadline, critical activities or float matter for management.

Better answers considered both the benefits and limitations of CPA and attempted to support their reasoning with information from the network.


Examiner hint: Build arguments such as 41-week project versus 45-week deadline → four-week margin → greater confidence that the deadline can be met, rather than simply quoting "41 weeks".

The 2021 mark scheme used specific quantitative evidence throughout its indicative content, including the 41-week completion time, critical activities C, D, F and G, and 16 weeks of float for several non-critical activities.


Examiner hint: Quantitative application can strengthen an extended CPA answer. Refer directly to the timings and float provided in the network.

The official judgement also emphasised that CPA remained a planning tool. If recruitment, training or another activity takes longer than estimated, the calculated completion time may no longer be achieved.


Examiner hint: A strong conclusion judges usefulness conditionally. CPA may be extremely valuable when the timing estimates are realistic and managers respond effectively to the information.

Common Mistakes ⚠️


Mistake: Choosing the smallest number when calculating EST


Why this is incorrect: When two routes meet, the next activity cannot start until all preceding activities are complete.


How to improve: For EST:


Work forwards and take the largest figure.

Mistake: Choosing the largest number when calculating LFT


Why this is incorrect: When working backwards, using the largest value could allow an earlier activity to finish too late for one of its successors.


How to improve: For LFT:


Work backwards and take the smallest figure.

Mistake: Identifying the shortest route as the critical path


Why this is incorrect: The critical path is the longest necessary sequence through the project because it determines the earliest possible completion date.


How to improve: Identify the route of zero-float activities and confirm that it determines the total project duration.


Mistake: Assuming a critical activity has lots of float


Why this is incorrect: Critical activities have:


$$

\boxed{0\text{ total float}}

$$


How to improve: If an activity has positive float, it is not critical within that network.


Mistake: Using the wrong values in the total-float formula


Why this is incorrect: You need the LFT at the end of the activity and the EST at its start.


How to improve:


\text{end LFT}

\text{duration}


\text{start EST}

$$


Mistake: Saying that float means an activity should be delayed


Why this is incorrect: Float shows that delay is possible without affecting the overall project schedule.


It does not mean delay is desirable.


How to improve: Describe float as scheduling flexibility.


Mistake: Describing the network instead of assessing CPA


Why this is incorrect: This was a major weakness identified in the 2021 examiner report.


How to improve: After every piece of network information, ask:


How does knowing this help the business manage the project?

Mistake: Assuming the calculated completion time is guaranteed


Why this is incorrect: Activity durations are estimates and unexpected events may occur.


How to improve: Use wording such as:


"The network suggests the project can be completed in..."

rather than:


"The project will definitely be completed in..."

Mistake: Assuming finishing faster is always better


Why this is incorrect: Edexcel's 2021 mark scheme specifically recognised the risk of prioritising speed at the expense of quality, such as inadequate employee training.


How to improve: Evaluate whether meeting the time target could create consequences elsewhere in the project.


Exam-Style Questions ✍️


Use the following information for Questions 1 to 8.


FreshBox Ltd is preparing to launch a new automated packing system. Its project contains the following activities:

Activity

From node

To node

Duration in weeks

A

1

2

3

B

1

3

5

C

2

4

4

D

3

4

3

E

4

5

2


The network is:

(1) ──A 3──> (2) ──C 4──> (4) ──E 2──> (5)
  \
   └─B 5──> (3) ──D 3────> (4)

FreshBox wants the project completed within 11 weeks. Management believes the automated system will help it process orders more efficiently, but the activity times are estimates and several employees will require training before the system is introduced.


Questions


1. Define Critical Path Analysis. (1 mark)


2. Calculate the Earliest Start Time at nodes 2, 3, 4 and 5. (4 marks)


3. Calculate the Latest Finish Time at nodes 4, 3, 2 and 1. (4 marks)


4. Identify FreshBox Ltd's critical path and state the minimum project completion time. (3 marks)


5. Calculate the total float for activities A and C. (4 marks)


6. Explain one benefit to FreshBox Ltd of identifying the critical path. (4 marks)


7. Assess the usefulness of total float to FreshBox Ltd when managing the project. (10 marks)


8. Assess the likely value of Critical Path Analysis to FreshBox Ltd when introducing the automated packing system. (12 marks)


Answers and Indicative Mark Scheme


Question 1


Critical Path Analysis is a project-planning technique used to organise the sequence and timing of activities and identify the route that determines the minimum completion time.


1 mark for an accurate definition.


Question 2


Node 2


$$

0+3=3

$$


Therefore:


$$

\boxed{EST_2=3}

$$


Node 3


$$

0+5=5

$$


Therefore:


$$

\boxed{EST_3=5}

$$


Node 4


Via A and C:


$$

3+4=7

$$


Via B and D:


$$

5+3=8

$$


Take the largest:


$$

\boxed{EST_4=8}

$$


Node 5


$$

8+2=10

$$


Therefore:


$$

\boxed{EST_5=10}

$$


Answers:

  • node 2 = 3

  • node 3 = 5

  • node 4 = 8

  • node 5 = 10


Maximum 4 marks.


Question 3


Final project duration:


$$

10

$$


Therefore:


$$

LFT_5=10

$$


Node 4


$$

10-2=8

$$


$$

\boxed{LFT_4=8}

$$


Node 3


$$

8-3=5

$$


$$

\boxed{LFT_3=5}

$$


Node 2


$$

8-4=4

$$


$$

\boxed{LFT_2=4}

$$


Node 1


Via A:


$$

4-3=1

$$


Via B:


$$

5-5=0

$$


Take the lowest:


$$

\boxed{LFT_1=0}

$$


Answers:

  • node 4 = 8

  • node 3 = 5

  • node 2 = 4

  • node 1 = 0


Maximum 4 marks.


Question 4


Path A, C, E:


$$

3+4+2=9

$$


Path B, D, E:


$$

5+3+2=10

$$


Therefore the critical path is:


$$

\boxed{B-D-E}

$$


Minimum project completion time:


$$

\boxed{10\text{ weeks}}

$$


FreshBox's target is 11 weeks, so the network suggests the project could finish:


$$

11-10=1\text{ week}

$$


before the deadline.


Question 5


Activity A


Start EST:


$$

0

$$


End LFT:


$$

4

$$


Duration:


$$

3

$$


Therefore:


\boxed{1\text{ week}}

$$


Activity C


Start EST:


$$

3

$$


End LFT:


$$

8

$$


Duration:


$$

4

$$


Therefore:


\boxed{1\text{ week}}

$$


Both activities have one week of total float.


Question 6


Possible answer:


Identifying the critical path shows FreshBox that activities B, D and E have no spare time. Managers can therefore monitor these activities particularly closely because a delay to one of them could delay the entire project beyond its planned ten-week completion time. This may help FreshBox achieve its 11-week target.


Indicative marking:

  • understanding of critical path: 1 mark

  • application to B, D, E or the ten-week project: up to 2 marks

  • developed consequence: 1 mark


Question 7


Why total float is useful


FreshBox can calculate that activities A and C each have:


$$

1\text{ week}

$$


of total float.


This means these activities have some scheduling flexibility.


Managers may therefore be able to:

  • tolerate a short delay to A or C

  • organise employee time around other activities

  • concentrate attention on B, D and E, which have zero float


Possible chain:


A has one week float → A can be delayed by up to one week without delaying project → management has greater flexibility in allocating resources


Float therefore helps distinguish between activities where timing is absolutely critical and those where some flexibility exists.


Limitations


The one-week figure depends on the activity durations being accurate.


For example:

  • employee training may take longer than expected

  • an activity could experience an unexpected delay

  • a one-week float could quickly be used up


Float also does not mean FreshBox should deliberately delay the activity.


Supported judgement


Total float is useful because it shows FreshBox exactly where some scheduling flexibility exists. However, the amount of float is only one week for A and C, so the margin is relatively small.


Its value therefore depends on the reliability of the estimated activity times and on management continuing to monitor the project as work progresses.


Question 8


Reasons CPA may be valuable


Identifies the project duration


CPA shows that the minimum planned completion time is:


$$

10\text{ weeks}

$$


FreshBox's target is:


$$

11\text{ weeks}

$$


Therefore the network suggests a:


$$

1\text{-week margin}

$$


This could reassure managers that the planned sequence is capable of meeting the deadline.


Identifies critical activities


The critical path is:


$$

B-D-E

$$


These activities have zero total float.


Possible chain:


critical activities identified → managers monitor B, D and E closely → reduced risk of unnoticed delay → greater chance of meeting 11-week deadline


Identifies float


Activities A and C each have:


$$

1\text{ week}

$$


of float.


This gives FreshBox some flexibility when organising those tasks.


Supports project planning


The network shows which activities can occur separately and which depend on other activities being completed first.


This may make the launch easier to coordinate.


Limitations


Timing estimates may be wrong


FreshBox's activity durations are only estimates.


If one of the critical activities takes longer:


critical activity delayed → zero float → project duration rises above ten weeks


With only a one-week margin before the 11-week deadline, a significant delay could cause the target to be missed.


Training may take longer


Several employees require training.


If training is part of a critical activity and managers underestimate the time required, the project may be delayed.


CPA cannot prevent unexpected problems


Equipment, employees or implementation could still create problems that were not anticipated in the network.


Speed versus quality


FreshBox should not rush employee training simply to preserve the ten-week completion time.


Poor training could reduce the effectiveness of the new automated system even if the project technically finishes on schedule.


Possible supported judgement


CPA is likely to be a valuable planning tool for FreshBox because it identifies a ten-week completion time, a one-week margin before the target and the specific activities that require the closest monitoring.


However, its value depends heavily on the accuracy of FreshBox's activity-duration estimates. Because the project has only a one-week margin, even a relatively small delay to the critical path could remove the advantage shown by the original network.


CPA should therefore help FreshBox plan and monitor the project, but the business should not treat the ten-week completion time as guaranteed. Effective management of the activities, especially employee training and other critical tasks, will ultimately determine whether the project succeeds.


Recent Posts

See All
The integrated marketing mix | AQA A-Level Business

For Specification 7132 AQA A-Level Business | Free Revision Notes Estimated study time: 50 to 60 minutes Effective marketing is not achieved by making seven separate decisions and hoping they work tog

 
 
 
Forms of business | AQA A-Level Business

For Specification 7132 AQA A-Level Business | Free Revision Notes Estimated study time: 35 minutes Businesses can operate under very different forms of ownership and organisation, and these difference

 
 
 

Comments


bottom of page