Amending network diagrams | AQA A-Level Business

Oct 15
23 min read

Updated: 12 hours ago


For Specification 7132


AQA A-Level Business | Free Revision Notes


Estimated study time: 40 to 45 minutes



Project plans do not always develop exactly as expected. An activity may take longer or less time than originally estimated, changing the project's critical path, available float and completion date. These Amending network diagrams A-Level Business revision notes explain how to update network information when activity timings change and how managers can use the revised information during strategic implementation. This builds directly on network analysis [Lesson 145. Network analysis] and critical paths and total float [Lesson 146. Critical paths and total float].


Learning Objectives 🎯


By the end of this revision page, you should be able to:

  • Interpret changes in activity timings.

  • Amend network diagrams when an activity duration changes.

  • Recalculate the duration of project routes.

  • Reassess the critical path following a change.

  • Recalculate relevant total float.

  • Analyse how changes in network information may affect strategic implementation decisions.


Revision Notes 📚


Amending network diagrams A-Level Business revision overview


AQA's network-analysis content includes:

  • understanding and interpreting network diagrams

  • amendment of network diagrams

  • identifying the critical path

  • identifying total float


The original network is based on expected activity durations.


However, strategic implementation takes place in an uncertain business environment.


An activity might:

  • take longer than expected

  • be completed more quickly

  • experience an unexpected delay


When this happens, managers need to reconsider the network.


The process can involve:


activity timing changes → network is amended → route durations are recalculated → critical path is reassessed → float may change → implementation decisions may need to change


The important principle is:


A network diagram is not fixed. If the information changes, the project analysis must also be updated.

Why might a network need to be amended?


Network diagrams contain estimates of how long project activities are expected to take.


Actual durations may differ.


For example:

  • equipment installation takes longer than expected

  • an approval process is completed early

  • a supplier causes a delay

  • an activity encounters an unexpected problem

  • work is completed more quickly than planned


If management continues using the original network after activity timings change, its information about:

  • the project duration

  • the critical path

  • available float

may become inaccurate.


Example


Original Activity E:


4 days


New information:


Activity E will take 7 days


Increase:


7 - 4 = 3 days


Management cannot simply add three days to the total project duration.


Whether the project completion date changes depends on:

  • whether E was critical

  • how much float E had

  • which route E belongs to

  • whether the longer duration creates a new critical path


This is why the whole network may need to be reconsidered.


First question: was the changed activity critical?


When an activity duration changes, identify whether it was originally:

  • on the critical path

  • off the critical path


This gives an initial indication of the likely effect.


If a critical activity takes longer


Critical activities have zero total float.


Therefore:


critical activity duration increases → no existing float to absorb increase → critical route becomes longer → project completion may also become later


For example:


Original critical path:


A → C → F = 16 days


C originally takes 8 days.


If C now takes 10 days:


A → C → F = 6 + 10 + 2 = 18 days


If no other network changes occur, the project duration increases from:


16 days to 18 days


If a non-critical activity takes longer


The result is less immediate.


A non-critical activity may have float.


For example:


Activity D has:


6 days total float


D becomes:


3 days longer


Since:


3-day increase < 6-day float


the increase can potentially be absorbed.


The overall project duration need not change.


Remaining float may fall to:


6 - 3 = 3 days


However, if D becomes longer by more than its available float, the route containing D may begin to affect overall completion.


Changes to non-critical activities can create new critical paths


This is one of the most important ideas in the topic.


Suppose the original routes are:


Route ACF = 16 days


Route BDF = 10 days


Route BEG = 15 days


The original critical path is:


ACF


because it is the longest route.


Now suppose Activity E increases by three days.


The route BEG becomes:


18 days


The routes are now:

  • ACF = 16

  • BDF = 10

  • BEG = 18


The new critical path is:


BEG


and the minimum project duration becomes:


18 days


The original critical path is no longer critical.


📌 Key principle: A change to a non-critical activity can alter the entire project's critical path.


AQA-style amended network example


An AQA network-analysis question has used the following activity durations:

Activity

Original duration

A

6 days

B

4 days

C

8 days

D

4 days

E

4 days

F

2 days

G

7 days


The three main routes are:


Route ACF


6 + 8 + 2 = 16 days


Route BDF


4 + 4 + 2 = 10 days


Route BEG


4 + 4 + 7 = 15 days


The original critical path is therefore:


ACF


with a duration of:


16 days


Now Activity E increases from:


4 days to 7 days


The amended BEG route becomes:


4 + 7 + 7 = 18 days


The revised routes are therefore:

Route

New duration

ACF

16 days

BDF

10 days

BEG

18 days


The amended critical path becomes:


BEG


and the new project duration becomes:


18 days


This demonstrates exactly why network information needs to be recalculated rather than simply assuming the old critical path remains unchanged.


A systematic method for amending a network


When an activity duration changes, use the following process.


Step 1: Identify the activity that changed


Write down:

  • original duration

  • new duration

  • amount of change


For example:


E: 4 days → 7 days


Increase:


+3 days


Step 2: Identify the route or routes containing the activity


Trace the activity through the network.


For example:


Activity E lies on:


B → E → G


Step 3: Recalculate affected route durations


Do not assume the project duration changes by exactly the same amount as the activity.


Calculate the whole route again.


Step 4: Compare all routes


The longest valid route after the amendment becomes the critical path.


Step 5: Recalculate project duration


The duration of the new critical path becomes the revised minimum project completion time.


Step 6: Recalculate relevant node timings if required


If the network diagram itself needs to be updated, the earliest and latest timings may also change.


Step 7: Recalculate relevant float


A change to activity timing or overall project duration can alter the amount of float elsewhere in the network.


Step 8: Interpret the business consequence


Ask:

  • Has the project deadline changed?

  • Are different activities now critical?

  • Has management flexibility increased or decreased?

  • Should resources be reallocated?

  • Does management need to revise implementation decisions?


Recalculating earliest times


When activity durations change, the earliest possible time at which later events can occur may also change.


Earliest times are recalculated by working:


from left to right


through the network.


One route entering a node


Suppose a node can only be reached through Activity A.


Starting time:


0


Activity A:


6 days


Earliest time at next node:


0 + 6 = 6


Two routes entering the same node


Suppose a later node can only be reached after two incoming routes have been completed.


Route 1 arrives at:


12 days


Route 2 arrives at:


15 days


The earliest time at that node is:


15 days


because the project cannot move beyond the event until the required incoming work has been completed.


Therefore:


When several required routes enter a node, use the largest arrival time for the earliest event time.

This reflects the dependency.


Recalculating latest times


Latest timings are reconsidered by working:


from right to left


through the network.


Begin with the revised project completion time.


If the amended critical path changes project completion from:


16 days to 18 days


the final node becomes:


18


for the revised timing.


You can then work backwards through the network to identify how late earlier events can occur without delaying the revised project completion.


One activity leaving a node


Suppose:

  • final permissible time at next node = 18

  • Activity G takes 7 days


Latest permissible time at the preceding node:


18 - 7 = 11


More than one activity leaving a node


If several activities leave a node, management needs the timing that ensures all required routes can still be completed.


Use the earliest allowable result.


For example:


Route through Activity X allows the event to occur by day 12.


Route through Activity Y requires it by day 10.


The latest time for the node must therefore be:


10 days


Otherwise the route requiring completion by day 10 would be delayed.


Worked amended timing example


Return to the earlier network.


Original activities:

  • A = 6

  • B = 4

  • C = 8

  • D = 4

  • E = 4

  • F = 2

  • G = 7


Original project duration:


16 days


Activity E is changed to:


7 days


Forward calculation


Start:


0


After A:


0 + 6 = 6


After B:


0 + 4 = 4


Route through A and C:


6 + 8 = 14


Route through B and D:


4 + 4 = 8


The joining event before F therefore cannot occur before:


14


because the A-C route takes longer.


Route through B and amended E:


4 + 7 = 11


Then G:


11 + 7 = 18


Route through F:


14 + 2 = 16


Final completion therefore becomes:


18 days


The new critical route is:


B → E → G


Recalculating float after an amendment


Changing one activity can alter float elsewhere.


Recall the formula:


Total float = latest time at end node - activity duration - earliest time at start node

Suppose the revised network produces:

  • earliest start node for D = 4

  • D still takes 4 days

  • revised latest end-node time = 16


Then:


Total float for D = 16 - 4 - 4


= 8 days


The float for D has increased compared with its original six days.


Why?


Because the whole project now takes longer due to the changed route through E.


The deadline for completing the project has moved later, creating additional spare time on some other non-critical activities.


This demonstrates an important principle:


A delay can reduce float on one route while increasing float elsewhere because the overall project timetable has changed.

Recalculating float for the changed activity


Suppose E is now on the critical path.


Its total float will be:


0


because:


B → E → G


now determines the overall project duration.


Originally E was non-critical.


After the amendment, it becomes critical.


This means management priorities may need to change.


Float can disappear after an amendment


Suppose Activity H originally has:


4 days of float


Its duration increases by four days.


The entire float is used.


New float:


0 days


H may now be critical or lie on a critical route.


If H experiences any further delay:


no spare time remains → overall project completion is threatened


Management should therefore change how closely the activity is monitored.


Float may be reduced without disappearing


Suppose:


Original float:


6 days


Activity duration increases by:


2 days


Remaining float:


4 days


The project deadline need not change, but management has less flexibility.


Analytical chain:


Activity duration increases → some float is used → scheduling flexibility falls → future delays become more significant → activity may require closer monitoring.


This is more useful than simply saying:


The activity still has float.

Reassessing the critical path


Whenever activity timings change, ask:

  1. What are the new route durations?

  2. Which route is now longest?

  3. Are two or more routes now equally long?

  4. Has the project duration changed?

  5. Which activities now have zero float?


Do not assume that the original critical path remains critical.


An amendment can create two critical paths


Suppose original routes are:

  • Route ACF = 20 days

  • Route BEG = 18 days


Critical path:


ACF


Now an activity on BEG increases by two days.


Revised routes:

  • ACF = 20

  • BEG = 20


There are now two critical paths.


This has important management consequences.


Before:


Only activities on ACF determine completion time


After:


Activities on both ACF and BEG determine completion time


This reduces scheduling flexibility.


A delay on either route could now delay the whole project.


An amendment can remove a critical path


Suppose a project originally has two critical paths of 20 days.


Management finds a way to reduce one route by three days.


The routes become:

  • Route ACF = 17 days

  • Route BEG = 20 days


Only:


BEG


remains critical.


Activities on ACF may now possess float.


This could increase management flexibility and change where resources are most urgently required.


When a critical activity becomes shorter


Changes are not always delays.


Suppose Activity C on the critical path is expected to take:


8 days


but managers discover that it will only take:


5 days


Original critical route:


A → C → F = 6 + 8 + 2 = 16


Revised:


A → C → F = 6 + 5 + 2 = 13


However, this does not automatically mean the entire project can finish in 13 days.


Another route may now be longer.


Suppose:


BEG = 15 days


After C is shortened:

  • ACF = 13 days

  • BEG = 15 days


The new critical path becomes:


BEG


The project duration falls only from:


16 days to 15 days


not to 13 days.


📌 Exam tip: Never calculate the effect of a changed critical activity in isolation. Compare the revised duration with all alternative routes.


How changes affect the minimum project completion time


There are several possibilities.


Outcome 1: Project duration increases


This may occur when:

  • a critical activity takes longer

  • a non-critical activity increases by more than its float

  • another route becomes the new longer critical route


Outcome 2: Project duration stays the same


This can occur when:

  • a non-critical activity is delayed by less than or equal to its float


For example:


4-day float + 3-day delay → overall completion unchanged


Outcome 3: Project duration decreases


This may occur if:

  • one or more critical activities are completed faster

  • no alternative route prevents the earlier completion


Outcome 4: Critical path changes but project duration does not


Suppose:


Original:

  • ACF = 16

  • BEG = 15


After ACF becomes one day shorter:

  • ACF = 15

  • BEG = 15


Project duration becomes 15 days, with both paths critical.


Alternatively, an adjustment could change which route is critical while maintaining the same total project duration depending on other route changes.


The important point is to recalculate the network rather than relying on assumptions.


Strategic significance of a changed critical path


A new critical path changes what management should treat as time-sensitive.


Suppose originally:


ACF is critical


Management prioritises Activities A, C and F.


After an amendment:


BEG becomes critical


Management may now need to prioritise:

  • B

  • E

  • G


This could affect:

  • allocation of employees

  • management attention

  • monitoring

  • communication

  • decisions about scarce resources


Therefore:


critical path changes → project priorities change → management decisions should also change


Resource allocation after an amendment


Suppose Activity E becomes critical.


Activity D now has substantial float.


Both require the same specialist employee.


Management might decide:


E is critical → delay would extend project completion → D has spare time → specialist employee moved from D to E → E receives priority → project deadline may be better protected.


However, this decision has a limitation.


If D is delayed too much:


float is used → D becomes critical → resource decision creates a new scheduling problem


Managers therefore need to consider the remaining float, not simply whether an activity is currently non-critical.


Amended networks and management attention


The network helps managers distinguish between activities that require different levels of attention.


Critical activity


Management may need:

  • frequent monitoring

  • rapid response to problems

  • priority access to scarce resources


Non-critical activity with little float


Still requires significant attention because a relatively small delay could make it critical.


Non-critical activity with substantial float


Management has more scheduling flexibility, although it should not be ignored.


The amendment can therefore change management priorities even when the actual tasks themselves remain unchanged.


Changes to deadlines


Strategic projects may have important deadlines.


For example:

  • opening a new facility

  • launching before a key selling period

  • entering a market before a competitor

  • implementing a new strategic system


Suppose a network amendment moves completion from:


20 weeks to 24 weeks


Managers must assess the consequence.


For example:


Project delayed by 4 weeks → planned market launch occurs after important sales period → expected revenue may fall → strategic value of project may be reduced.


The significance of a network amendment therefore depends on the business context.


A four-week delay is not equally important for every project.


Competitor actions can increase the significance of delays


Suppose two businesses are racing to introduce similar products.


Critical path increases → launch delayed → competitor enters market first → competitor may gain customers → strategic implementation becomes less valuable.


In this situation, managers might be willing to commit extra resources to critical activities.


In a project with no urgent competitive deadline, the same delay might be less significant.


Financial consequences of a network amendment


A longer project may create additional costs.


For example:


Project duration increases → employees and resources needed for longer → implementation costs may rise → expected return from strategy may fall.


However, management should not automatically attempt to reduce the delay at any cost.


Moving extra resources to critical activities can itself be expensive.


Managers therefore need to consider:


cost of delay versus cost of corrective action


Quality and timing


A network focuses heavily on timing.


Management should avoid sacrificing other strategic objectives simply to restore the original completion date.


For example:


Critical activity delayed → management rushes work → quality falls → strategic project is completed on time but performs poorly.


This means the fastest amended schedule is not automatically the best managerial choice.


Time must be considered alongside:

  • quality

  • cost

  • strategic objectives


Amendments and strategic implementation


AQA places network analysis within strategic implementation because strategies often need to be adjusted as actual events differ from plans.


Suppose a business is implementing a new production facility.


Original plan:


24 weeks


Unexpected delay:


Activity K takes 3 weeks longer


Network analysis can show whether:

  • the delay can be absorbed by float

  • the project duration changes

  • a new critical path emerges


Managers can then decide what action is required.


This is far more useful than simply knowing that "K is three weeks late".


Network amendments and leadership


An amended network provides information.


Managers still need leadership to decide how to respond.


For example:


New critical path identified → several activities now need additional attention → leader decides which resources to prioritise → revised implementation plan communicated.


This links to implementing strategy [Lesson 143. Implementing strategy].


Network analysis informs decisions. Leadership determines the response.


Network amendments and communication


When activity timings change, other teams may be affected.


For example:


Activity E delayed → Activity G cannot start at planned time → employees responsible for G need revised information → schedules and resources may need to change.


Poor communication could mean:


network updated centrally → affected employees are not informed → teams continue following old timetable → disruption increases.


Amending the diagram therefore creates little value unless revised information reaches the relevant people.


Network amendments and organisational structure


Managers may need to react quickly when critical activities change.


If the organisational structure creates slow approval processes:


critical activity develops problem → local manager identifies solution → senior approval required → response delayed → project falls further behind.


A suitable organisational structure can therefore affect how effectively network information is used.


This connects with organisational structure and implementation [Lesson 144. Organisational structure and implementation].


Network analysis does not remove uncertainty


Updating the network improves the plan using the latest information.


It does not guarantee that no further changes will occur.


For example:


E revised from 4 days to 7 days → network amended → later G also experiences delay → network must be reconsidered again.


Network analysis is therefore an ongoing management tool.


Managers should be prepared to update the project as implementation develops.


The value of continually updating a network


More accurate project information


The network reflects current expectations rather than outdated estimates.


Better identification of priorities


Managers can identify the activities that are currently critical.


More effective resource decisions


Resources can be directed according to revised float and critical-path information.


Better monitoring


Management can compare actual progress with the latest project plan.


Improved response to change


The organisation can adjust implementation rather than continuing to follow a plan that is no longer realistic.


These benefits connect network analysis with the wider idea of organisational flexibility.


Limitations of amending the network


Revised timings are still estimates


A revised duration may also prove inaccurate.


Frequent changes can create complexity


If several activities keep changing, managers may need to amend the network repeatedly.


Changing the diagram does not solve the cause of delay


For example:


Specialist employee unavailable → network amended → employee remains unavailable


The diagram reflects the problem but does not remove it.


Resources may prevent corrective action


Management may know that a critical activity needs additional resources but lack the finance, labour or equipment required.


Other implementation factors remain important


Strategic implementation still depends on:

  • leadership

  • communication

  • organisational structure

  • employee cooperation


An accurate amended network is only one management tool.


Interpreting a delay using float


When an activity is delayed, compare:


size of delay with total float

Example 1


Float:


5 days


Delay:


2 days


Result:


2 < 5


Project completion does not have to change.


Remaining float:


3 days


Example 2


Float:


5 days


Delay:


5 days


Result:


All float is used.


Project completion can remain unchanged, but the activity now has no spare time.


Example 3


Float:


5 days


Delay:


8 days


Excess delay:


8 - 5 = 3 days


The route is now three days beyond its previous allowable timing.


Managers must recalculate the network to see whether:

  • project duration increases

  • a new critical path emerges


Do not use float mechanically


A useful shortcut is:


delay less than float → project deadline unaffected


but always remember that network timings can interact.


For larger or more complex amendments, recalculate the routes and relevant node timings.


The safest examination method is:

  1. calculate the size of the change

  2. compare it with float

  3. recalculate the affected route

  4. compare it with other routes


Worked example: delay within float


A project has:


Critical path ACF = 22 days


Another route:


BDG = 18 days


An activity on BDG is delayed by:


3 days


New route:


18 + 3 = 21 days


Comparison:

  • ACF = 22

  • BDG = 21


The critical path remains:


ACF


Project duration remains:


22 days


The delay has been absorbed by spare time.


Worked example: delay creates equal critical paths


Original:

  • ACF = 22

  • BDG = 18


Activity on BDG delayed by:


4 days


New route:


22 days


Now:

  • ACF = 22

  • BDG = 22


There are two critical paths.


Project duration remains:


22 days


However, management flexibility has decreased.


Previously BDG had four days of spare time.


Now it has none.


Worked example: delay creates a longer project


Original:

  • ACF = 22

  • BDG = 18


Activity on BDG delayed by:


6 days


New route:


24 days


Now:

  • ACF = 22

  • BDG = 24


New critical path:


BDG


New project duration:


24 days


Project completion has been delayed by:


2 days


Notice that the activity itself was delayed by six days, but the project was delayed by only two because the route originally contained four days of spare time.


This is a crucial interpretation skill.


Worked example: activity completed early


Original routes:

  • ACF = 20

  • BEG = 18


ACF is critical.


Suppose critical Activity C is completed:


3 days faster


New ACF:


17 days


Now compare:

  • ACF = 17

  • BEG = 18


New critical path:


BEG


New project duration:


18 days


The critical activity improved by three days, but the total project duration improved by only:


2 days


because another route now determines completion.


Recalculate rather than assume


These examples demonstrate why common shortcuts can fail.


Wrong assumption


A critical activity becomes three days faster, so the project becomes three days faster.

Not necessarily.


Correct approach


Change activity duration → recalculate its route → compare all routes → identify new critical path → determine revised completion time


Likewise:


Wrong assumption


A non-critical activity is delayed, so the project is delayed.

Not necessarily.


The activity may have sufficient float.


Management decisions following an amendment


Managers may respond in several ways depending on the revised information.


Continue without action


Appropriate where:

  • delay is within available float

  • project completion remains unaffected


Increase monitoring


Appropriate where:

  • most float has been used

  • activity is close to becoming critical


Reallocate resources


Appropriate where:

  • a newly critical activity requires support

  • other activities possess sufficient float


Revise the project timetable


Necessary where:

  • completion date has genuinely changed

  • the original timetable is no longer realistic


Communicate the change


Affected employees and managers need to understand the revised timings.


The network identifies what has changed. Management must then act on it.


Should managers always try to restore the original deadline?


No.


Suppose restoring the deadline requires substantial additional expenditure.


Managers need to compare:


cost of late completion


with


cost of speeding up implementation


For example:


Situation A


A two-week delay means missing an important seasonal sales period.


The cost of delay may be substantial.


Management may justify extra spending.


Situation B


A two-week delay creates little effect on customers or revenue.


Expensive corrective action may not be worthwhile.


The network provides timing information, but managerial judgement remains essential.


Using amended network information in evaluation


A strong evaluative answer should consider:

  • how much the timing changed

  • whether the activity was originally critical

  • available float

  • whether the critical path changed

  • urgency of project completion

  • availability and cost of resources

  • strategic consequences of delay


For example:


The three-day increase in Activity E is strategically significant because it changes the critical path and moves project completion from 16 to 18 days. If the project has a fixed launch deadline, management may need to prioritise resources towards E and G. If the deadline is flexible, accepting the additional two days may be less costly than reallocating scarce resources.

This is much stronger than:


The delay is bad because the project takes longer.

How to answer an AQA network-amendment question


For a one-mark question


Give the answer directly.


For example:


New critical path = BEG


For a duration question


Show the route calculation if space permits:


B + E + G = 4 + 7 + 7 = 18 days


For float


Write:


Total float = latest end time - duration - earliest start time


Then substitute the figures.


For an analyse question


Use the network information in a chain:


Activity duration increases → available float is used → activity becomes critical → management has no spare time for further delay → closer monitoring may be required → strategic deadline is more vulnerable


For evaluation


Add context:

  • How urgent is completion?

  • Is the delay costly?

  • Can resources be moved?

  • Are activity estimates reliable?

  • Does the critical path change?


📌 Exam tip: Always recalculate before explaining the business consequence. If the network calculation is wrong, the rest of the analysis may be based on an incorrect project position.


Key Words 🔑

Key word

Student-friendly definition

How it may be used in an exam

Amended network

A network diagram or project analysis updated to reflect changed activity information.

Recalculate timings, critical paths and float when project information changes.

Critical path

The sequence of activities determining the minimum project completion time.

Reassess which route becomes critical after an activity duration changes.

Total float

The amount of time an activity can be delayed without delaying overall project completion, assuming other timings remain unchanged.

Assess how much of a delay can be absorbed before the project timetable is threatened.

Activity duration

The expected time required to complete a project activity.

Replace the original timing with revised information and recalculate the network.

Project duration

The minimum completion time determined by the current critical path.

Compare the original and revised completion times after an amendment.


Common Mistakes ⚠️


Mistake: Adding the entire activity delay to the project duration


Why this is incorrect: A non-critical activity may have float that absorbs some or all of the delay.


How to improve: Compare the activity's delay with its float and recalculate the route.


Mistake: Keeping the original critical path automatically


Why this is incorrect: Another route may become longer after an amendment.


How to improve: Recalculate every affected route and compare it with the existing critical route.


Mistake: Assuming a change to a critical activity changes the project by exactly the same amount


Why this is incorrect: Another route can become the new critical path.


How to improve: Always compare the revised route against the alternative routes.


Mistake: Assuming a non-critical activity cannot become critical


Why this is incorrect: A sufficiently large increase in its duration can use all available float and create a new critical path.


How to improve: Reassess the whole network after the timing changes.


Mistake: Forgetting that float itself can change


Why this is incorrect: Changing the project duration or node timings can alter float elsewhere in the network.


How to improve: Recalculate relevant float using the revised timings.


Mistake: Treating an activity delayed by exactly its float as immediately delaying the project


Why this is incorrect: The activity can use all of its float without necessarily delaying overall completion.


How to improve: Recognise that it now has zero float, making any further delay particularly significant.


Mistake: Focusing only on the arithmetic


Why this is incorrect: Network analysis is included within strategic implementation.


How to improve: Explain how revised information affects:

  • resources

  • monitoring

  • project deadlines

  • implementation decisions


Mistake: Assuming an amended network solves the delay


Why this is incorrect: The network identifies and measures the effect. Managers still need to decide how to respond.


How to improve: Separate:


project information


from


management action


Exam-Style Questions ✍️


Question 1


A project originally has the following routes:

  • ACF = 19 days

  • BDG = 17 days


Activity D now takes 3 days longer.


Calculate the revised duration of BDG and identify the new critical path. [2 marks]


Question 2


Activity K has 5 days of total float. It is now expected to take 3 days longer than originally planned.


Calculate the amount of float remaining. [2 marks]


Question 3


An activity has 4 days of total float and is delayed by exactly 4 days.


Explain the implication for the project. [3 marks]


Question 4


A critical activity originally takes 7 days but is now expected to take 10 days.


Explain why management should not automatically assume that the total project duration will increase by exactly 3 days. [3 marks]


Question 5


A project contains these routes:

Route

Original duration

ACF

21 days

BDG

16 days

BEH

19 days


Activity E lies on route BEH and is now expected to take 4 days longer.


a) Calculate the revised duration of BEH. [1 mark]

b) Identify the new critical path or paths. [1 mark]

c) State the revised minimum project duration. [1 mark]


Question 6


Northstar Ltd


Northstar Ltd is implementing a new distribution strategy.


Activity F originally had six days of total float. It is now expected to take four days longer.


Analyse the implications of this change for Northstar Ltd's project management. [9 marks]


Question 7


VisionTech plc


VisionTech plc is implementing a new digital production system.


Its original network contained:

  • critical path ACF = 24 weeks

  • route BEG = 21 weeks


An unexpected problem means an activity on BEG will now take five weeks longer.


The project must be completed before the start of VisionTech's busiest selling period.


Analyse the implications of the change for VisionTech plc's strategic implementation. [9 marks]


Question 8


Harbour Foods Ltd


Harbour Foods Ltd is implementing a strategic project to open a new production facility.


The original project had a minimum duration of 30 weeks.


During implementation:

  • an activity with significant float has been delayed

  • another activity is now expected to take longer than planned

  • management believes the critical path may have changed

  • specialist employees can be moved between activities, but doing so increases costs

  • a competitor is planning to open a similar facility


Evaluate the importance of continually amending the network diagram during Harbour Foods Ltd's strategic implementation. [16 marks]


Answers and indicative mark scheme


Question 1


Original BDG:


17 days


Activity D increases by:


3 days


Revised BDG:


17 + 3 = 20 days


Compare:

  • ACF = 19

  • BDG = 20


Therefore:


New critical path = BDG


New project duration = 20 days


Question 2


Original float:


5 days


Increase in activity duration:


3 days


Remaining float:


5 - 3 = 2 days


Answer: 2 days


Question 3


The activity uses all four days of its available float.


Therefore:


4-day delay = 4-day float


The overall project completion date need not change, assuming other timings remain unchanged.


However, the activity now has:


0 days float


Any further delay could therefore threaten the project's completion time.


Question 4


The critical route containing the activity becomes three days longer, but another route may become critical.


For example:


critical route becomes longer or shorter relative to alternative routes → another path may determine completion → total project duration must be found by recalculating and comparing all routes.


Management should therefore revise the whole network rather than simply adding three days to the previous project duration.


Question 5


Original BEH:


19 days


E takes:


4 days longer


a)


Revised BEH:


19 + 4 = 23 days


b)


Compare:

  • ACF = 21

  • BDG = 16

  • BEH = 23


New critical path = BEH


c)


Revised project duration = 23 days


Question 6


Activity F originally has six days of float.


It is expected to take four days longer.


Therefore:


4-day increase < 6-day float


The increase can potentially be absorbed without delaying Northstar's overall project.


Remaining float becomes:


6 - 4 = 2 days


This means the change is not currently enough to alter project completion, assuming other timings remain unchanged.


However, F now has much less scheduling flexibility.


A possible analytical chain is:


Activity takes four days longer → most of its float is used → only two days spare time remain → further delays become more significant → management may need to monitor F more closely.


Northstar may therefore avoid an immediate expensive response because the project deadline has not yet changed.


However, ignoring F completely could be risky because another delay of more than two days could make the route critical.


Question 7


Original routes:

  • ACF = 24 weeks

  • BEG = 21 weeks


An activity on BEG takes:


5 weeks longer


New BEG:


21 + 5 = 26 weeks


The new critical path therefore becomes:


BEG


and project duration increases from:


24 weeks to 26 weeks


This means VisionTech's project is now expected to take two weeks longer overall.


The difference matters because completion must occur before its busiest selling period.


A possible chain is:


New critical path = 26 weeks → project completion delayed by two weeks → production system may not be operational for busiest period → VisionTech could have less capacity or efficiency when demand is highest → potential sales or profit may be affected.


Management may therefore consider reallocating resources towards critical activities.


However:


Additional resources used → implementation cost rises → financial benefit of completing sooner may be reduced.


The best decision depends on how valuable the busy selling period is compared with the cost of restoring the timetable.


Question 8


Continually amending the network could be highly valuable because Harbour's original 30-week plan is becoming outdated.


One activity has already been delayed and another duration has changed.


Therefore:


original timings become inaccurate → original critical path may no longer determine completion → managers could prioritise the wrong activities unless the network is updated.


Amending the network enables Harbour to:

  • identify the new critical path

  • calculate the revised project duration

  • recalculate relevant float

  • identify activities that now require closer monitoring

  • make better-informed resource decisions


This is particularly useful because specialist employees can be moved between activities.


For example:


New critical activity identified → non-critical activity retains float → specialist employee can be moved towards critical activity → delay may be reduced → opening date may be protected.


The competitor increases the strategic importance of timing.


Harbour opens late → competitor may open first → competitor could establish customer relationships earlier → strategic value of Harbour's project may fall.


However, continually updating the network has limitations.


Activity timings remain estimates. Another unexpected change could make the revised network inaccurate again.


Moving specialist employees also increases costs.


Network identifies opportunity to accelerate project → resources moved → implementation cost rises → profitability of strategy may fall.


Harbour must therefore consider whether the benefit of earlier completion outweighs the extra cost.


The network also does not solve underlying implementation problems. Successful implementation still depends on factors such as:

  • leadership

  • communication

  • availability of resources

  • employee cooperation


Evaluation:


Continual amendment is likely to be particularly important for Harbour because the project environment is already changing and timing has strategic significance due to the competitor.

Using the original network after activity durations have changed could lead management to monitor the wrong activities and misunderstand the true completion date.


However, the value comes from using the revised information to make sensible decisions, not from repeatedly redrawing the network for its own sake.


Harbour should therefore update the network whenever a change is significant enough to affect route durations, float or the critical path, and then compare the strategic value of protecting the project deadline with the costs of corrective action.

Recent Posts

See All
The integrated marketing mix | AQA A-Level Business

For Specification 7132 AQA A-Level Business | Free Revision Notes Estimated study time: 50 to 60 minutes Effective marketing is not achieved by making seven separate decisions and hoping they work tog

 
 
 
Forms of business | AQA A-Level Business

For Specification 7132 AQA A-Level Business | Free Revision Notes Estimated study time: 35 minutes Businesses can operate under very different forms of ownership and organisation, and these difference

 
 
 

Comments


bottom of page