Network analysis | AQA A-Level Business
Updated: 12 hours ago
For Specification 7132
AQA A-Level Business | Free Revision Notes
Estimated study time: 35 to 40 minutes
Strategic decisions often involve projects containing several activities that must be completed in a particular order. Network analysis gives managers a way to represent these activities, their timings and their dependencies visually. These Network analysis A-Level Business revision notes explain how to understand and interpret the network diagrams used by AQA and how network analysis can support strategic implementation. This builds directly on implementing strategy [Lesson 143. Implementing strategy]. Calculating critical paths and total float is covered separately in critical paths and total float [Lesson 146. Critical paths and total float].
Learning Objectives 🎯
By the end of this revision page, you should be able to:
Explain the purpose of network analysis.
Understand the main features of an AQA network diagram.
Identify activities and their durations.
Identify dependencies between activities.
Interpret the order in which project activities must occur.
Analyse how network analysis can support strategic implementation.
Revision Notes 📚
Network analysis A-Level Business revision overview
AQA requires students to understand the value of network analysis in strategic implementation.
The specification includes:
understanding and interpreting network diagrams
amendment of network diagrams
identifying the critical path
identifying total float
This lesson concentrates on the first of these: understanding and interpreting the network.
The remaining skills are developed in:
critical paths and total float [Lesson 146. Critical paths and total float]
amending network diagrams [Lesson 147. Amending network diagrams]
Network analysis is useful because implementing a strategy may involve many interconnected activities.
For example, a new product launch could require:
product development
production preparation
marketing activity
distribution arrangements
Some activities may be completed at the same time.
Others cannot start until an earlier activity has finished.
Network analysis helps managers understand these relationships.
What is network analysis?
Network analysis is a project-planning technique that represents the activities involved in a project and the order in which they need to occur.
It allows managers to see:
the individual activities involved
how long activities are expected to take
which activities depend on others
which activities can take place simultaneously
the sequence through which the project progresses
Later analysis can also identify:
the critical path
total float
These become particularly important when managers are trying to complete strategic implementation within a particular timescale.
Why networks are useful for strategic implementation
A strategic objective may be broad.
For example:
Launch a new product.
Managers cannot implement this simply by stating the objective.
The project has to be divided into activities.
For example:
Develop product → prepare production → complete launch activities → product enters market
Network analysis helps management organise these activities into a logical sequence.
Understanding an AQA network diagram
The supplied AQA past papers use network diagrams in which:
circles represent numbered events or nodes
arrows represent activities
each activity is identified by a letter
the time taken for an activity is shown with the activity
arrows show the direction in which the project progresses
A simplified example might look like this:
1 → A (4 days) → 2 → C (3 days) → 4
while another route could be:
1 → B (2 days) → 3 → D (5 days) → 4
This means the project contains four activities:
A
B
C
D
and the arrows show how they are connected.
The direction of the arrows
Always read the network in the direction of the arrows.
If the diagram shows:
1 → A → 2 → C → 4
then:
A takes place before C
C cannot begin until the event following A has been reached
Reading the arrows in the wrong direction will produce an incorrect interpretation of the project.
Activities
An activity is a task within the project.
In AQA network diagrams, activities are shown as arrows labelled with letters.
For example:
A 6
would indicate an activity labelled A taking 6 units of time, such as six days if the question states that all timings are in days.
A network might contain:
Activity A
Activity B
Activity C
Activity D
Each represents a different piece of work required to complete the project.
Activity duration
The activity duration tells managers how long that activity is expected to take.
For example:
Activity B = 4 days
means that once Activity B can begin, it is expected to take four days to complete.
Managers can use these timings when considering the overall project schedule.
Nodes or events
AQA network diagrams use numbered circles between activities.
A node marks a point reached within the project.
For example:
Node 1 → Activity A → Node 2
Activity A occurs between Node 1 and Node 2.
The numbered nodes therefore help managers follow the sequence through the project.
Timing information inside nodes
In the AQA network diagrams used in the supplied past papers, nodes can contain:
an event number
an earliest timing
a latest timing
For example, a node might appear with:
5 as the event number
14 as the earliest timing
14 as the latest timing
You should be able to recognise these parts of a network.
Calculating and using these timings to determine the critical path and total float is covered in [Lesson 146. Critical paths and total float].
📌 For this lesson: concentrate on understanding what the diagram shows and how activities depend on one another.
What is a dependency?
A dependency exists when one activity cannot begin until another required activity has been completed.
Dependencies are one of the most important features of network analysis.
Suppose the network shows:
A → C
This indicates that C occurs after A.
If C cannot start until A has been completed, C is dependent on A.
Simple dependency
Consider:
Start → A → B → Finish
B depends on A.
The sequence is:
Activity A completed → Activity B can begin
If A is delayed, B may also be delayed because B cannot simply begin independently.
Why dependencies matter
Strategic projects often contain activities that rely on the completion of earlier work.
For example, suppose a business is preparing a new product.
It may need to:
complete product development
prepare production
begin full production
Production cannot necessarily begin before development has been completed.
Network analysis makes that dependency visible.
Immediate predecessors
An activity that must occur before another activity can begin can be described as a preceding activity.
Consider:
A → C → E
Here:
A comes before C
C comes before E
C is therefore directly dependent on A, while E is directly dependent on C.
A delay earlier in the sequence may consequently affect later activities.
This is one reason managers need to understand the complete network rather than considering every activity independently.
Activities that can occur at the same time
Not all activities have to be completed one after another.
A network may branch.
For example:
Start → A
and at the same time:
Start → B
If neither activity depends on the other, A and B may be able to take place simultaneously.
This is important because project duration is not calculated simply by adding the duration of every activity.
Some activities may occur at the same time.
Example
Suppose:
Activity A takes 6 days
Activity B takes 4 days
If A and B can begin at the same time, management does not necessarily need ten days to complete both.
This is one of the key reasons a network diagram provides more useful information than a simple list of project activities.
When several activities meet at one node
A network may have more than one arrow entering the same node.
For example:
A → C ↘
B → D → Node 5
This means the project routes come together at Node 5.
An activity leaving Node 5 cannot begin until the requirements represented by the incoming activities have been completed.
This is a very important dependency.
Example
Suppose Activity F begins from a node that can only be reached after Activities C and D.
Then:
C completed + D completed → F can begin
It is not enough for only C to be complete if D is also required before that event is reached.
Why this matters
Suppose:
C finishes on time
D is delayed
F may still be unable to begin.
Therefore:
Delay to dependent activity → later activity cannot start → implementation timetable may be affected.
Network analysis makes these relationships visible before or during the project.
Reading a network systematically
When given a network diagram, follow a consistent process.
Step 1: Find the starting node
Identify where the network begins.
Step 2: Follow the arrows
Never work backwards unless the question specifically requires it.
Step 3: Identify each activity
Look for the letters attached to the arrows.
Step 4: Identify activity durations
Read the timing shown for each activity.
Step 5: Identify branches
Look for situations where several activities can begin from the same event.
These activities may be capable of occurring alongside one another.
Step 6: Identify dependencies
Ask:
What must have happened before this activity can start?
Step 7: Look for points where routes join
If several activities feed into one event, identify what must be completed before the project can progress beyond that point.
This systematic approach prepares you for later calculations.
Worked example
Consider the following project.
Activity A: 4 days
Activity B: 3 days
Activity C: 5 days
Activity D: 2 days
Activity E: 3 days
The network is arranged so that:
A is followed by C
B is followed by D
C and D must both be completed before E begins
What can we interpret?
A and B
A and B begin from the start of the project.
Neither is shown as dependent on the other.
They may therefore be completed alongside one another.
C
C follows A.
Therefore:
A completed → C can begin
C is dependent on A.
D
D follows B.
Therefore:
B completed → D can begin
D is dependent on B.
E
E occurs after the two branches meet.
Therefore:
C and D completed → E can begin
E depends on the completion of both routes into the joining event.
Why is this useful?
Management can now see that the project is not simply:
A → B → C → D → E
Some activities can occur simultaneously.
The network shows the actual sequence and dependencies.
That makes project planning much more useful.
Network analysis and strategic implementation
Network analysis is included by AQA specifically because of its value in strategic implementation.
Breaking strategy into manageable activities
A major strategy can appear difficult to manage as one large objective.
Network analysis allows managers to break implementation into separate tasks.
For example:
Strategy: introduce new production facility
could involve separate activities relating to:
preparing the site
installing equipment
preparing operations
completing other launch requirements
A network can then show how those activities relate.
This may make a complex strategic project easier to plan.
Showing the sequence of implementation
Some activities have to occur in a particular order.
Network analysis makes that sequence clear.
For example:
Earlier activity completed → dependent activity begins → next stage of implementation progresses
This can reduce the risk that managers attempt activities before their prerequisites have been completed.
Example
Suppose a strategic project requires Activity C to follow Activity A.
Without understanding this dependency:
Manager attempts C too early → required earlier work is incomplete → project is disrupted.
A network diagram can make the relationship clear before implementation begins.
Identifying which activities can occur simultaneously
One potential advantage of network analysis is that managers can see where different activities do not have to wait for each other.
For example:
Activity A and Activity B have no dependency between them → both can progress at the same time → strategic project can advance through several routes simultaneously.
This can help managers organise the implementation schedule more effectively.
Improving coordination
Strategic implementation can involve different employees, managers or parts of the organisation.
A network provides a common view of:
what needs to happen
in what order
which activities depend on others
For example:
Managers understand dependencies → teams know when their activity can begin → activities can be coordinated → implementation may be less disrupted.
This links to communication in strategic implementation [Lesson 143. Implementing strategy].
Supporting communication
A visual network can help communicate the structure of a project.
Instead of each team seeing only its own activity, managers can see how individual activities contribute to the whole implementation process.
For example:
Team sees that another activity depends on its work → understands consequence of delay → coordination between teams may improve.
Network analysis therefore supports communication by showing interdependence.
Highlighting the consequences of delays
Even before calculating critical paths and float, managers can use the network to understand that delays may have knock-on effects.
For example:
Activity A delayed → C cannot begin → later dependent activity also starts later.
The full significance of individual delays depends on:
where the activity sits in the network
whether alternative time is available
whether the activity is critical
These issues are covered through critical paths and total float [Lesson 146. Critical paths and total float].
Supporting resource planning
A network shows when activities are expected to occur in relation to one another.
This can help managers think about where project resources may be required.
For example:
Two activities need to occur simultaneously → both require management attention → business must consider whether sufficient resources are available.
However, a network diagram itself does not guarantee that those resources exist.
Management still needs to make appropriate resource decisions.
Supporting monitoring
Once implementation begins, managers can compare project progress with the network.
For example:
Activity expected to be complete → actual progress checked → delay identified → managers assess implications for dependent activities.
Network analysis can therefore support management both:
before implementation
during implementation
The value of identifying dependencies
Dependencies can be strategically important because a delay in one area may prevent another area from starting.
Suppose a strategic project contains:
A → C → E
If A is late:
A delayed → C starts late → E may also be affected
This means managers need to understand relationships between activities, not just the performance of each activity individually.
A team could complete its own activity efficiently but still be unable to proceed because another dependent activity has not finished.
Network analysis and management decision making
Network analysis provides managers with information.
However, it does not make decisions for them.
For example, a network may show:
activities
timings
dependencies
Managers still need to decide:
how resources should be allocated
what should happen if an activity is delayed
whether the project plan needs to change
how employees should be coordinated
Therefore:
Network information → management interpretation → decision → implementation response
The value depends partly on how effectively managers use the information.
Network analysis is based on estimated timings
Activities in a project often have expected durations.
The actual time required may differ.
For example:
Activity estimated at 5 days → unexpected problem occurs → actual duration becomes 8 days.
The original network then needs to be reconsidered.
This is why AQA also requires students to understand the amendment of network diagrams [Lesson 147. Amending network diagrams].
Network analysis should therefore not be treated as a perfect prediction of the future.
Advantages of network analysis for strategic implementation
Provides a clear project overview
Managers can see how different activities contribute to the project.
Shows dependencies
It identifies which activities rely on the completion of others.
Shows activities that can occur simultaneously
This can help managers understand how the project can progress through several routes.
Supports coordination
Managers and teams can understand when their activities fit into the overall implementation process.
Supports communication
The network can provide a shared representation of the implementation plan.
Helps managers consider delays
Dependencies make it easier to see why a delay in one activity may affect later work.
Provides the basis for further project analysis
Once the network is understood, managers can identify:
the critical path
total float
These provide additional information for managing implementation.
Limitations of network analysis
Activity times may be inaccurate
A network depends on expected activity durations.
If these estimates are inaccurate, the planned project timings may also be inaccurate.
For example:
Activity expected to take 4 days → actually takes 7 days → original project plan becomes less accurate.
Unexpected events can change the project
Strategic implementation occurs in uncertain conditions.
Unexpected:
operational problems
external changes
resource difficulties
may alter the original network.
Managers may therefore need to amend it.
The network does not complete the project
A well-designed network is a planning tool.
It cannot itself:
motivate employees
provide resources
overcome resistance
lead the organisation
For example:
Network accurately identifies activity sequence → employees resist strategic change → activities are still delayed.
This links back to leadership and communication in strategic implementation [Lesson 143. Implementing strategy].
It depends on correct identification of dependencies
If management misunderstands which activities depend on others, the network may not accurately represent the project.
Poor information at the planning stage can therefore reduce its usefulness.
Complex projects may produce complex networks
As the number of activities and dependencies increases, interpreting the network may become more demanding.
Managers still need to focus on the most important implementation information.
Network analysis should not be used in isolation
Network analysis is one part of strategic implementation.
Successful implementation may also require:
effective leadership
communication
suitable organisational structure
management of resistance
appropriate organisational culture
For example:
Network identifies when activities should happen → organisational structure prevents quick decisions → implementation still slows.
Or:
Network shows dependencies clearly → teams communicate poorly → one team is unaware another is waiting for its activity → delay still occurs.
Network analysis is therefore most useful when combined with effective management.
Network analysis and organisational structure
The organisation must be capable of carrying out the activities shown on the network.
For example:
Network requires rapid coordination between functions → functional departments communicate poorly → project activities become disconnected → implementation is delayed.
Management may therefore need to consider whether its organisational structure supports the project.
This links directly to organisational structure and implementation [Lesson 144. Organisational structure and implementation].
Network analysis and communication
Dependencies create a need for communication.
Suppose Activity D cannot begin until Activity B is completed.
The people responsible for D need to know when B has finished.
Therefore:
Activities are dependent → teams need information about progress → effective communication supports handover → implementation is better coordinated.
A network identifies the dependency, but communication allows employees to act on it.
Network analysis and leadership
Managers may need to respond when the project does not progress as expected.
For example:
Activity takes longer than planned → network implications identified → leader decides how resources or implementation should respond.
Network analysis supplies useful information.
Leadership determines what action is taken.
Interpreting an AQA-style network
The supplied AQA past papers provide useful examples of how networks are presented.
In one official network:
Activity A took 6 days
Activity B took 4 days
A and B began from the starting event
Activity C followed A
Activities D and E followed the lower route
later activities brought the different routes towards completion
The network therefore required students to interpret:
activity sequence
timings
alternative routes
relationships between activities
AQA then used this same type of diagram to test critical paths, float and the effect of changing activity duration.
The essential first skill is therefore accurately reading the network.
Preparing for critical path analysis
Once you can confidently identify:
activities
durations
routes
dependencies
joining points
you are ready to identify the most time-sensitive route through the project.
This is the critical path, covered in [Lesson 146. Critical paths and total float].
For now, remember:
A network diagram is not simply a picture of activities. It shows the logical relationships between them.
How to answer a network-analysis question
If asked to identify an activity
Find the labelled arrow.
If asked for its duration
Read the number attached to that activity.
If asked what an activity depends on
Trace backwards through the arrows to identify what must be completed before it can begin.
If asked what can happen simultaneously
Look for separate activities that can begin without one depending on the other.
If asked how network analysis supports implementation
Develop the business consequence:
dependencies identified → managers know correct activity sequence → activities can be coordinated → delays caused by starting work at the wrong time may be reduced → strategic implementation becomes more effective
📌 Exam tip: Move beyond saying that a network "helps planning". Explain what information it provides and how managers use that information during implementation.
Key Words 🔑
Key word | Student-friendly definition | How it may be used in an exam |
Network analysis | A project-planning technique that shows project activities, timings and the order in which activities need to occur. | Analyse how a business can plan and coordinate strategic implementation. |
Activity | A task that must be completed as part of a project. | Identify activities and their durations from arrows on a network diagram. |
Dependency | A relationship where an activity depends on required earlier activity being completed. | Explain why one activity cannot begin until another stage of the project has finished. |
Node | A numbered event point within an AQA network diagram connecting project activities. | Use nodes to follow the sequence through a network. |
Activity duration | The amount of time an activity is expected to take. | Interpret the timings shown alongside activities in a network diagram. |
Common Mistakes ⚠️
Mistake: Treating the nodes as the activities
Why this is incorrect: In the AQA networks shown in the supplied papers, the arrows represent activities. The numbered circles are events or nodes.
How to improve: Look for the activity letter attached to an arrow.
Mistake: Reading the network backwards
Why this is incorrect: The direction of the arrows shows how the project progresses.
How to improve: Start at the initial node and follow the arrows towards completion.
Mistake: Assuming every activity happens one after another
Why this is incorrect: Networks can branch, allowing activities on separate routes to occur at the same time.
How to improve: Look for activities beginning from the same event without depending on each other.
Mistake: Missing a dependency at a joining node
Why this is incorrect: If several required activities enter the same event, later work may need to wait until all necessary incoming activities are complete.
How to improve: Check every arrow entering a node before moving to the next activity.
Mistake: Adding every activity duration together
Why this is incorrect: Some activities may take place simultaneously on different routes.
How to improve: Follow the actual routes through the network rather than treating the project as one long list.
Mistake: Saying network analysis "helps planning" without development
Why this is incorrect: This does not analyse its value.
How to improve: Explain the mechanism:
network identifies dependencies → managers understand activity sequence → teams can be coordinated → implementation may be less delayed
Mistake: Assuming the network guarantees completion on time
Why this is incorrect: Activity durations are estimates and unexpected events can change implementation.
How to improve: Treat network analysis as a management tool, not a guarantee.
Exam-Style Questions ✍️
Question 1
What is meant by network analysis? [2 marks]
Question 2
In an AQA network diagram, what do the labelled arrows represent? [1 mark]
Question 3
A network contains the following sequence:
Start → A → B → C → Finish
Which activity must be completed immediately before Activity C can begin? [1 mark]
Question 4
A project contains two activities, A and B, that can both begin at the start of the network and do not depend on one another.
Explain what this indicates about the timing of Activities A and B. [3 marks]
Question 5
Consider the following project:
Activity A is followed by Activity C.
Activity B is followed by Activity D.
Activities C and D must both be completed before Activity E can begin.
Identify:
a) the activity that C immediately depends on [1 mark]
b) the activity that D immediately depends on [1 mark]
c) the two activities that must be completed before E can begin [2 marks]
Question 6
Nova Foods Ltd
Nova Foods Ltd is implementing a strategy to launch a new product.
The project contains several activities carried out by its marketing and operations teams. Some activities can occur simultaneously, while other activities cannot begin until earlier tasks have been completed.
Analyse one reason why network analysis could support the successful implementation of Nova Foods Ltd's strategy. [9 marks]
Question 7
EcoBuild Ltd
EcoBuild Ltd is implementing a major expansion project.
Managers have created a network diagram showing:
12 separate activities
the expected duration of each activity
several activities that depend on earlier work
three activities that can be completed simultaneously
Analyse two ways in which the network could help EcoBuild Ltd manage the project. [9 marks]
Question 8
Velocity plc
Velocity plc is implementing a new production strategy.
Its directors have produced a detailed network diagram, but:
some activity durations are only estimates
several departments communicate poorly with each other
employees are resistant to parts of the new strategy
Evaluate the value of network analysis to Velocity plc when implementing its strategy. [16 marks]
Answers and indicative mark scheme
Question 1
Network analysis is a project-planning technique that shows project activities, timings and the order or dependencies between activities.
2 marks: Clear understanding of project activities and their sequence or relationships.
1 mark: Partial understanding.
Question 2
The labelled arrows represent activities.
1 mark
Question 3
Activity B
1 mark
Question 4
A and B do not depend on one another and can both begin from the start of the project.
This means they may be carried out at the same time rather than one having to wait for the other.
Indicative marking:
recognises no dependency, 1 mark
recognises simultaneous activity, 1 mark
explains implication for project timing, 1 mark
Question 5
a) A [1 mark]
b) B [1 mark]
c) C and D [2 marks]
Question 6
Network analysis can help Nova Foods identify dependencies between launch activities.
For example:
Operations activity depends on an earlier product-preparation activity → dependency is shown on the network → managers know that operations cannot begin until the earlier task is completed → activities can be scheduled in the correct order → disruption or wasted resources may be reduced.
The fact that some activities can happen simultaneously may also help Nova Foods understand how different teams can progress at the same time.
This could support a more coordinated launch.
A strong response should connect the network directly to strategic implementation, rather than simply saying that it helps planning.
Question 7
One benefit is identifying dependencies:
Earlier activity must be completed before later activity → network makes relationship clear → managers can coordinate the handover between teams → risk of starting an activity too early may fall.
A second benefit is identifying activities that can take place simultaneously:
Three activities do not need to wait for one another → managers can organise them at the same time → several parts of the project can progress simultaneously → implementation may be completed more efficiently.
The activity durations also give managers information about the expected timetable and can help them monitor whether work is progressing as planned.
Question 8
Arguments supporting the value of network analysis include:
it breaks the strategic project into identifiable activities
it shows expected activity durations
it identifies dependencies
it highlights which activities can occur simultaneously
it can support coordination between departments
it provides a basis for monitoring progress
later analysis can identify critical activities and float
For example:
Dependency identified → department understands that another activity must finish first → work is scheduled correctly → disruption may be reduced → implementation becomes more effective.
However, the value is limited by Velocity's circumstances.
Activity durations are estimates:
Estimated duration inaccurate → actual project timing differs from network → original plan becomes less reliable.
Communication is also weak:
Network shows dependency → departments fail to communicate progress → team does not know earlier activity is delayed → coordination still fails.
Employee resistance creates another limitation:
Network accurately plans activities → employees do not support strategic change → implementation is delayed regardless of the quality of the network.
Evaluation:
Network analysis is likely to be valuable to Velocity because a major production strategy may involve many dependent activities that need to be coordinated.
However, it is a planning and management tool, not a complete solution to implementation.
Its value will be much greater if Velocity also:
improves communication
manages employee resistance
updates the network when activity timings change
The strongest judgement is therefore that network analysis can significantly improve the organisation and monitoring of strategic implementation, but its usefulness depends on the quality of the underlying estimates and management's ability to act on the information the network provides.