Critical paths and total float | AQA A-Level Business
Updated: 1 day ago
For Specification 7132
AQA A-Level Business | Free Revision Notes
Estimated study time: 40 to 45 minutes
A network diagram becomes much more useful when managers can identify which activities are most important to the project's completion time. These Critical paths and total float A-Level Business revision notes explain how to identify the critical path, calculate total float and use this information to support strategic implementation. AQA specifically requires students to identify the critical path and total float as part of network analysis. This lesson builds directly on understanding network diagrams [Lesson 145. Network analysis] before moving to changes in project timings in amending network diagrams [Lesson 147. Amending network diagrams].
Learning Objectives 🎯
By the end of this revision page, you should be able to:
Identify the critical path through a network diagram.
Calculate the duration of a critical path.
Calculate total float for an activity.
Interpret critical-path information.
Analyse the significance of float for project management.
Use network information to support strategic implementation decisions.
Revision Notes 📚
Critical paths and total float A-Level Business revision overview
AQA's network-analysis content requires students to understand:
network diagrams
amendment of network diagrams
the critical path
total float
Two ideas are central to this lesson:
Critical path: the sequence of activities that determines the minimum time required to complete the project.
Total float: the amount of time by which a non-critical activity can be delayed without delaying completion of the overall project, assuming the rest of the network remains unchanged.
The critical path is important because a delay to a critical activity can delay the whole project.
Float is important because it shows managers where some scheduling flexibility exists.
Recap: reading an AQA network diagram
AQA network diagrams use:
arrows for activities
letters to identify activities
numbers to show activity durations
nodes or events between activities
timing information inside the nodes
A typical node includes:
the event number on the left
an earliest time in the upper-right section
a latest time in the lower-right section
These timings help determine:
which route is critical
how much float an activity possesses
Before attempting calculations, make sure you can follow the network accurately from its start to its finish.
What is the critical path?
The critical path is the sequence of activities that determines the shortest possible completion time for the whole project.
It is normally the longest-duration route through the network.
This may initially sound strange.
Why does the longest route determine the shortest completion time?
Because all activities required by the network have to be completed. The project cannot finish before its longest necessary sequence of dependent activities has finished.
For example, suppose a project contains two routes:
Route 1 takes 14 days
Route 2 takes 18 days
Even if Route 1 finishes after 14 days, the entire project cannot be complete because Route 2 still requires four more days.
Therefore:
Project minimum completion time = 18 days
and Route 2 is the critical path.
Critical activities
Activities on the critical path are called critical activities.
A critical activity has zero total float.
This means there is no spare time available for that activity if the project is to retain its planned minimum completion time.
For example:
Critical activity delayed by 2 days → dependent critical activities begin later → project completion may also be delayed by 2 days.
This assumes management does not take some other action that changes the network or recovers the lost time.
📌 Key principle: Critical activities require particularly close management attention because there is no scheduling flexibility built into them.
There can be more than one critical path
Do not assume every network contains only one critical path.
Two different routes could take exactly the same amount of time.
For example:
A → C → F = 16 days
B → D → G = 16 days
Both routes could be critical.
This means more activities have no float and management has less flexibility.
AQA has tested networks where several activities appear on critical paths, so always inspect the whole diagram rather than assuming one route must be uniquely critical.
How to identify the critical path
There are two useful approaches.
Method 1: Compare the routes
Follow every valid route from the start node to the finishing node.
Add the duration of the activities on each route.
The longest valid route is the critical path.
For example:
Route A → C → F
6 + 8 + 2 = 16 days
Route B → E → G
4 + 4 + 7 = 15 days
The critical path is therefore:
A → C → F
and the minimum project duration is:
16 days
Method 2: Identify zero-float activities
Activities on the critical path have zero total float.
If the network provides earliest and latest timings, you can calculate float for individual activities.
Activities with zero float form the critical route or routes through the project.
Both methods should lead to the same answer.
Calculating critical-path duration
Once the critical path has been identified:
Critical-path duration = sum of the activity durations on the critical path
Example
Critical path:
A → C → F
Activity durations:
A = 6 days
C = 8 days
F = 2 days
Calculation:
6 + 8 + 2 = 16 days
The minimum project completion time is therefore 16 days.
Exam technique
Show the route and calculation clearly:
ACF = 6 + 8 + 2 = 16 days
This makes your reasoning easy to follow.
What is total float?
Total float is the amount of time by which an activity can be delayed without delaying the completion of the overall project, assuming other timings remain unchanged.
An activity with:
0 days float is critical
2 days float could be delayed by up to 2 days without changing the overall completion date
6 days float has considerably more scheduling flexibility
Float therefore shows managers where spare time exists within the project.
The total float formula
For an activity between two nodes:
Total float = latest time at the end node - activity duration - earliest time at the start node
A useful shorthand is:
Total float = LFT - duration - EST
where:
LFT is the latest permitted time at the node where the activity finishes
EST is the earliest time at the node where the activity begins
Important
Use:
the earliest time from the starting node
the latest time from the ending node
Do not take both values from the same node.
Worked float calculation
Suppose Activity D:
begins from a node with an earliest time of 4
takes 4 days
finishes at a node with a latest time of 14
The calculation is:
Total float = 14 - 4 - 4
Total float = 6 days
Activity D can therefore be delayed by up to 6 days without delaying completion of the overall project, assuming the other project timings remain unchanged.
This exact style of calculation has appeared in AQA assessment.
Another total float example
Activity E:
earliest time at starting node = 4
duration = 4 days
latest time at ending node = 9
Calculation:
Total float = 9 - 4 - 4
Total float = 1 day
This means Activity E has only one day of scheduling flexibility.
If E is delayed by:
1 day, overall completion need not change
more than 1 day, the overall project may be delayed unless another part of the schedule changes
Calculating float for a critical activity
Suppose Activity C:
begins at earliest time 6
duration = 8
finishes at latest time 14
Calculation:
Total float = 14 - 8 - 6
Total float = 0 days
Activity C is therefore critical.
A delay to C cannot be absorbed by spare time within its existing schedule.
Worked AQA-style network
Consider a project containing these activities:
Activity | Duration |
A | 6 days |
B | 4 days |
C | 8 days |
D | 4 days |
E | 4 days |
F | 2 days |
G | 7 days |
The routes are:
A → C → F
6 + 8 + 2 = 16 days
B → D → F
4 + 4 + 2 = 10 days
B → E → G
4 + 4 + 7 = 15 days
Therefore:
Critical path = ACF
Project duration = 16 days
Float for Activity D
Suppose:
earliest time at D's starting node = 4
latest time at D's ending node = 14
D lasts 4 days
Then:
Total float = 14 - 4 - 4
Total float = 6 days
D is not critical.
Float for Activity E
Suppose:
earliest starting time = 4
latest ending time = 9
duration = 4
Then:
Total float = 9 - 4 - 4
Total float = 1 day
E is also not critical, but it has much less spare time than D.
Interpreting different amounts of float
Float should not simply be calculated and forgotten.
Managers can use it when making project decisions.
Zero float
An activity with zero float is critical.
For example:
Activity A has 0 days float → A is delayed → no spare time exists to absorb delay → project completion may be delayed.
Management may therefore monitor A closely.
Small amount of float
Suppose Activity E has one day of float.
Management has limited flexibility.
A short delay may be absorbed, but a longer delay could affect the project.
Large amount of float
Suppose Activity D has six days of float.
This gives management greater scheduling flexibility.
For example, some resources allocated to D might temporarily be used elsewhere if doing so does not cause D to exceed its available float.
Float and resource allocation
One of the most important uses of float is helping managers think about where scarce resources should be concentrated.
Suppose:
Activity A is critical
Activity D has six days of float
both activities require the same specialist employee
Management might decide:
Critical activity requires specialist resource → non-critical activity has spare time → resource temporarily moved from D to A → A remains on schedule → D can be completed later using available float → overall project deadline may be protected.
This demonstrates why float information can support strategic implementation.
However, managers must be careful.
Using too much float removes the flexibility available later.
Float is a buffer
Float acts as a time buffer for non-critical activities.
For example:
Activity has 5 days total float → unexpected 2-day delay occurs → 3 days float remains → overall completion date need not change.
This can make project management more flexible.
But once the float has been used:
Remaining float falls → future delay becomes more dangerous → activity requires closer monitoring.
Managers therefore need to monitor how much float remains during implementation.
Float and prioritisation
Network information can help management prioritise activities.
Suppose managers have limited time to monitor a large project.
They might pay particularly close attention to:
critical activities
activities with very little float
activities on which many later tasks depend
The reasoning is:
Activity has little or no float → delay is difficult to absorb → greater risk to completion date → management attention may be more valuable.
This does not mean non-critical activities should be ignored.
If a non-critical activity uses all of its float, it can become critical.
Why the critical path matters to managers
It identifies the minimum project duration
Managers know the earliest time at which the whole project can be completed under the current plan.
This may be important when a strategy has a deadline.
For example:
New product must launch before key selling period → critical path shows minimum project duration → managers can judge whether planned launch date is achievable.
It identifies time-sensitive activities
Managers can focus attention on the activities where delays cannot be absorbed.
It supports monitoring
Managers can compare actual progress with expected progress.
If a critical activity falls behind:
Delay identified → manager recognises immediate threat to project completion → corrective action can be considered sooner.
It supports implementation decisions
Managers may use critical-path information when deciding:
where to allocate resources
which delays require the fastest response
whether the deadline remains achievable
whether the project plan needs amendment
Why float matters to managers
It identifies scheduling flexibility
Managers can see which activities have spare time.
It can support resource movement
Resources may potentially be shifted from activities with float towards more urgent critical activities.
It helps assess the significance of delays
A two-day delay means very different things depending on the available float.
Activity X
Float = 6 daysDelay = 2 days
The delay can potentially be absorbed.
Activity Y
Float = 0 days
Delay = 2 days
The overall project is at risk of being delayed.
The size of the delay alone is therefore not enough.
Managers need to compare:
delay versus available float
Using float when a delay occurs
Suppose Activity B has four days of total float.
Delay of two days
2-day delay < 4-day float
The project deadline need not change.
Remaining float:
4 - 2 = 2 days
Delay of four days
All available float is used.
Activity B can still potentially finish without delaying the project, but there is now no spare time remaining.
Delay of six days
6-day delay - 4-day float = 2 days beyond available float
The overall project may now be delayed by two days, unless management changes other activities or the network.
This becomes especially important in amending network diagrams [Lesson 147. Amending network diagrams].
A delay can create a new critical path
The critical path is based on current timings.
If the duration of a non-critical activity increases substantially, another route may become longer.
For example:
Original routes:
ACF = 16 days
BEG = 15 days
Original critical path:
ACF
Suppose Activity E becomes 3 days longer.
BEG becomes:
4 + 7 + 7 = 18 days
The new critical path becomes:
BEG
and project duration becomes:
18 days
This type of change has been directly tested by AQA.
The lesson is important:
Critical-path information is not permanent. If activity timings change, managers need to reassess the network.
More than one route can become critical
Suppose:
Route ACF = 16 days
Route BEG = 15 days
If an activity on BEG increases by one day:
ACF = 16
BEG = 16
There are now two critical paths.
This reduces management flexibility because both routes determine the completion time.
A delay on either critical route could delay the whole project.
Critical path and strategic implementation
AQA places network analysis within strategic implementation.
This means calculations should be connected back to management decisions.
Suppose a business is implementing a new production facility.
The critical path shows that several installation activities have no float.
Management might conclude:
Installation activities are critical → delays would threaten planned opening date → managers monitor these activities closely → resources can be prioritised towards them → risk of late implementation may fall.
This is much stronger than simply stating:
The critical path is ABC.
The calculation gives management information that can support action.
Critical path and leadership
Network information does not make decisions automatically.
A manager still needs to decide how to respond.
For example:
Critical activity delayed → network identifies likely project delay → leader decides whether resources should be moved → implementation plan adjusted.
This links with leadership in strategic implementation [Lesson 143. Implementing strategy].
Critical path and communication
Different teams may depend on one another.
If Activity F cannot begin until critical Activity C is finished:
C experiences delay → team responsible for F needs information → schedule can be adjusted → disruption may be managed.
The network identifies the relationship, but effective communication allows people to respond to it.
Critical path and organisational structure
A project may require decisions to be taken quickly when critical activities experience problems.
If every response requires lengthy senior approval:
Critical activity encounters difficulty → manager cannot act locally → decision delayed → critical-path delay becomes larger → implementation timetable worsens.
A suitable organisational structure can therefore affect how effectively managers use network information.
This links to organisational structure and implementation [Lesson 144. Organisational structure and implementation].
Limitations of critical-path information
Activity durations are estimates
A critical-path calculation is only as accurate as the timings used.
If an activity expected to take four days actually takes eight:
Original network no longer reflects reality → critical path may change → original completion estimate becomes inaccurate.
The critical path may change
A delay on a non-critical route can use its float and create a new critical path.
Managers must therefore continue monitoring the whole project.
Resources may not be available
A manager may identify a critical activity but still lack the:
employees
finance
equipment
needed to accelerate it.
Network analysis identifies the scheduling problem. It does not automatically solve the resource problem.
Focusing only on critical activities may be dangerous
A non-critical activity can become critical if its float is used.
Therefore:
Non-critical activity ignored → delay exceeds float → route becomes critical → project completion is threatened.
Managers need to monitor the whole network, even if critical activities receive particular attention.
Shortest completion time is not the only objective
A strategic project may also involve:
cost
quality
employee effects
For example, moving additional resources onto a critical activity may reduce delay but increase costs.
Management decisions should therefore consider wider strategic objectives.
Critical path versus importance to the business
A critical activity is critical to the timing of the project.
This does not necessarily mean it is the most financially expensive or strategically significant activity by every measure.
For example:
Activity A may be very expensive but have float
Activity B may be relatively inexpensive but lie on the critical path
Activity B is critical because delaying it threatens the completion date.
Do not confuse:
critical to project timing
with:
largest, most expensive or most difficult activity
Common critical-path calculation approach
When a network question appears:
Step 1: Trace each route
Follow the arrows from start to finish.
Step 2: Add the durations
Calculate the duration of each valid route.
Step 3: Identify the longest route
This is the critical path.
Step 4: State the activities clearly
For example:
Critical path = ACF
Step 5: State the project duration if required
For example:
6 + 8 + 2 = 16 days
Step 6: Calculate float if requested
Use:
Total float = latest end-node time - duration - earliest start-node time
Step 7: Interpret the answer
Explain what the float or critical path means for project management.
Worked calculation set
Consider this network information:
Activity | Duration | Earliest time at start node | Latest time at end node |
A | 5 | 0 | 5 |
B | 3 | 0 | 7 |
C | 6 | 5 | 11 |
D | 4 | 3 | 11 |
E | 2 | 11 | 13 |
Activity A
Total float = 5 - 5 - 0
= 0 days
A is critical.
Activity B
Total float = 7 - 3 - 0
= 4 days
B has scheduling flexibility.
Activity C
Total float = 11 - 6 - 5
= 0 days
C is critical.
Activity D
Total float = 11 - 4 - 3
= 4 days
D is non-critical.
Activity E
Total float = 13 - 2 - 11
= 0 days
E is critical.
A possible critical route therefore contains:
A → C → E
Project duration:
5 + 6 + 2 = 13 days
Interpreting the worked example
Management should pay close attention to A, C and E because they have no float.
Suppose C is delayed by two days:
C has zero float → delay cannot be absorbed → E begins later → project completion may move from day 13 to day 15.
Suppose B is delayed by two days:
B has four days float → delay can potentially be absorbed → overall completion date need not change → B still has two days of float remaining.
This comparison demonstrates the managerial value of float information.
How network information can support implementation decisions
Decision 1: Where should management attention be concentrated?
Critical activities and activities with little float may require closer monitoring.
Decision 2: Where might resources be moved from?
An activity with substantial float may have greater scheduling flexibility.
Decision 3: Does a delay threaten the deadline?
Compare delay with float.
Decision 4: Is the original completion date still achievable?
Recalculate routes if an activity duration changes.
Decision 5: Has the critical path changed?
A previously non-critical route may become critical.
Decision 6: Does the network need to be amended?
If activity durations change, management should update its plan rather than continue using outdated information.
These decisions lead directly into amending network diagrams [Lesson 147. Amending network diagrams].
Evaluating the value of critical-path information
Critical path and float can be valuable because they help managers understand:
minimum project duration
activities with no scheduling flexibility
activities where some delay is possible
where closer monitoring may be required
where resources might potentially be reallocated
However, their usefulness depends on:
accuracy of activity-duration estimates
whether managers update the network
availability of resources
quality of communication
management's response to new information
A perfect calculation does not guarantee successful implementation.
📌 Exam tip: If asked to analyse the value of float, do not stop at "it tells the business how long an activity can be delayed". Continue:
float identifies spare time → management can prioritise scarce resources → critical activities are more likely to remain on schedule → project completion date may be protected
Key Words 🔑
Key word | Student-friendly definition | How it may be used in an exam |
Critical path | The sequence of activities that determines the minimum time needed to complete a project. | Identify the longest-duration route and use it to assess project timing. |
Critical activity | An activity on a critical path with zero total float. | Explain why a delay may affect overall project completion. |
Total float | The amount of time an activity can be delayed without delaying overall project completion, assuming other timings remain unchanged. | Calculate spare time and analyse project-management flexibility. |
Project duration | The minimum time required to complete the project under the current network plan. | Calculate the sum of durations on the critical path. |
Activity duration | The expected amount of time needed to complete an activity. | Use timings to identify routes, critical activities and float. |
Hints from the Examiner Reports 💡
state activities on a critical path
calculate float for an activity
identify whether an activity is on a critical path
determine how a delay affects critical-path duration
identify a new critical path after an activity duration changes
AQA has also tested the principle that a network does not necessarily have to contain an activity with float, so do not assume every project must contain non-critical activities.
📌 Exam hint: These can be very short questions. A simple arithmetic or route-reading error may therefore lose the entire mark, so check the direction of the arrows and your calculation carefully.
Common Mistakes ⚠️
Mistake: Choosing the shortest route as the critical path
Why this is incorrect: The project cannot finish until its longest necessary sequence of dependent activities is complete.
How to improve: Add the durations of each valid route and identify the longest route.
Mistake: Assuming there can only be one critical path
Why this is incorrect: Two or more routes can have the same maximum duration.
How to improve: Check every valid route through the network.
Mistake: Assuming at least one activity must have float
Why this is incorrect: A network can contain several critical paths and it is possible for all activities to be critical.
How to improve: Calculate from the network rather than assuming some activities must have spare time.
Mistake: Using the wrong node timings in the float formula
Why this is incorrect: You need the earliest time at the starting node and the latest time at the ending node.
How to improve: Write the formula before substituting numbers:
Total float = latest end time - duration - earliest start time
Mistake: Forgetting to subtract the activity duration
Why this is incorrect: Float is not simply the difference between the two node timings.
How to improve: Use all three values.
Mistake: Assuming a critical activity can be delayed without consequence
Why this is incorrect: Critical activities have zero total float.
How to improve: A delay to a critical activity threatens the overall completion date unless management can recover the lost time elsewhere.
Mistake: Assuming every delay delays the whole project
Why this is incorrect: A non-critical activity may possess enough float to absorb a delay.
How to improve: Compare:
delay with available float
before deciding whether overall completion changes.
Mistake: Ignoring non-critical activities
Why this is incorrect: A non-critical activity can use its float and become critical.
How to improve: Prioritise critical activities but continue monitoring the whole network.
Mistake: Giving a calculation without interpretation
Why this is incorrect: A longer question may require you to explain what the network information means for management.
How to improve: Move from:
float = 4 days
to:
4 days spare time → activity can absorb some delay → management has greater scheduling flexibility → resources may potentially be prioritised elsewhere
Exam-Style Questions ✍️
Question 1
A project's three possible routes take:
Route ACF = 19 days
Route ADE = 14 days
Route BGE = 17 days
Identify the critical path and state the minimum project duration. [2 marks]
Question 2
Activity D begins from a node with an earliest time of 5 days. It takes 6 days and finishes at a node with a latest time of 15 days.
Calculate the total float for Activity D. [2 marks]
Question 3
An activity has zero total float.
Explain one implication of this for project management. [3 marks]
Question 4
Activity X has five days of total float and is delayed by three days.
Explain the likely effect of this delay on the project's planned completion date. [3 marks]
Question 5
A project contains the following routes:
Route | Activities and durations |
Route 1 | A = 4, C = 7, F = 3 |
Route 2 | B = 5, D = 3, F = 3 |
Route 3 | B = 5, E = 6, G = 4 |
a) Calculate the duration of each route. [3 marks]
b) Identify the critical path. [1 mark]
c) State the minimum project duration. [1 mark]
Question 6
NovaTech Ltd
NovaTech Ltd is implementing a strategic project. Activity H is on the critical path, while Activity J has six days of total float.
Both activities require the same specialist employees.
Analyse how NovaTech Ltd could use this network information when allocating employees. [9 marks]
Question 7
FreshFoods plc
FreshFoods plc is preparing to open a new production facility.
Its project network has a planned critical-path duration of 24 weeks.
Activity M:
is not currently critical
has 4 weeks of total float
is now expected to take 7 weeks rather than its original 4 weeks
Analyse the significance of this change for FreshFoods plc's project management. [9 marks]
Question 8
Omni Retail plc
Omni Retail plc is implementing a major digital strategy.
Its directors use network analysis to manage the project. The critical path is currently 30 weeks.
The directors know that:
several critical activities rely on specialist employees
some non-critical activities have significant float
activity timings are estimates
competitors are also investing rapidly in digital technology
Evaluate the importance of critical-path and total-float information to Omni Retail plc's strategic implementation. [16 marks]
Answers and indicative mark scheme
Question 1
The longest route is:
ACF = 19 days
Therefore:
Critical path = ACF
Minimum project duration = 19 days
1 mark for the correct critical path.
1 mark for the correct duration.
Question 2
Formula:
Total float = latest end time - duration - earliest start time
Calculation:
15 - 6 - 5 = 4 days
Answer: 4 days
Award credit for correct calculation and answer.
Question 3
An activity with zero total float is a critical activity.
Therefore:
Activity delayed → there is no spare time to absorb the delay → project completion may also be delayed.
Question 4
Activity X has five days of float but is delayed by only three days.
Therefore:
3-day delay < 5-day float
The delay can be absorbed within the existing schedule, assuming other timings do not change.
The planned project completion date therefore need not change.
Remaining float:
5 - 3 = 2 days
Question 5
a) Route durations
Route 1: ACF
4 + 7 + 3 = 14
Route 2: BDF
5 + 3 + 3 = 11
Route 3: BEG
5 + 6 + 4 = 15
b) Critical path
BEG
c) Minimum project duration
15 time units
Question 6
Activity H is critical, so it has no scheduling flexibility.
Activity J has six days of float.
NovaTech could potentially prioritise specialist employees towards H.
A possible chain is:
H is critical → delay to H threatens overall project completion → J has six days spare time → specialist employees may temporarily be moved from J to H → H is more likely to remain on schedule → overall project deadline may be protected.
The float on J gives management flexibility because J does not necessarily have to be completed at its earliest possible time.
However, NovaTech must not use more than the available float without considering the consequences.
J uses all six days float → no scheduling flexibility remains → any further delay could make J critical.
Management should therefore monitor both activities rather than completely ignoring J.
Question 7
Activity M originally has four weeks of float.
Its duration increases from four weeks to seven weeks, an increase of:
7 - 4 = 3 weeks
If nothing else changes, the three-week increase is within M's four weeks of float.
Therefore:
Duration increases by 3 weeks → 3 of 4 weeks float is used → project completion need not initially change → M has only 1 week of scheduling flexibility remaining.
This is significant because M is now much closer to becoming critical.
A further delay of more than one week could threaten the 24-week project duration.
Management may therefore need to:
monitor M more closely
reconsider resources
reassess the network if timings change again
A strong answer recognises that the increased duration does not automatically delay the entire project because M originally had sufficient float.
Question 8
Critical-path information is valuable because Omni Retail can identify the activities that determine its 30-week minimum implementation period.
Critical activities identified → management knows where delays cannot be absorbed → specialist employees can be prioritised → risk of exceeding the 30-week timetable may fall.
This is particularly important because competitors are also investing rapidly.
Critical activity delayed → digital strategy launches later → competitors may complete investment sooner → Omni's competitive position could weaken.
Total float also helps resource allocation.
Non-critical activity has substantial float → some work may be delayed within available spare time → specialist resources can be redirected towards critical activities → project deadline may be protected.
Float also allows managers to assess the significance of delays rather than treating every delay equally.
However, the information has limitations.
The activity timings are estimates:
Estimated duration proves inaccurate → current critical path may change → 30-week completion estimate becomes unreliable.
A non-critical route may also become critical if enough float is used.
Omni therefore cannot focus exclusively on its existing critical activities.
Other factors also affect implementation:
employee skills
communication
leadership
organisational structure
resistance to change
For example:
Network identifies correct priority → specialist employee is unavailable → management cannot implement the planned response → project may still be delayed.
Evaluation:
Critical-path and total-float information is likely to be highly valuable to Omni because the business faces a time-sensitive strategic project and scarce specialist employees. The information helps management distinguish between activities where delay can be tolerated and those where it cannot.
Its greatest value is therefore not the calculation itself, but the management decisions it supports, particularly monitoring and resource prioritisation.
However, because timings are estimates and competitors are changing the environment while implementation is taking place, Omni must update the network as new information emerges.
Critical-path analysis should therefore be treated as a dynamic project-management tool, not as a fixed guarantee that the strategy will be implemented in exactly 30 weeks.